Press Release – Bitdeer Announces November 2024 Production and Operations Update
|
Bitdeer Technologies Group
|
||
|
||
By:
|
/s/ Jihan Wu
|
|
Name:
|
Jihan Wu
|
|
Title:
|
Chief Executive Officer
|
|
|
|
|
Date: December 5, 2024 |
|
|
•
|
Self-mined Bitcoin: 150 bitcoins.
|
•
|
Mining Rig Manufacturing and R&D:
|
o
|
SEALMINER A1: Mass production of approximately 3.7 EH/s of mining rigs is on track with 0.1 EH/s powered on, 0.4 EH/s delivered for installation, 0.3 EH/s in-transit to data centers and 2.6 EH/s in production.
|
o
|
SEALMINER A2:
|
o
|
Secured wafer capacity as of this report date is expected to generate approximately 35 EH/s hashrate in 2025, increased from 18 EH/s.
|
o
|
Initial allocation of ~30,000 units (~7 EH/s out of the 35 EH/s) of SEALMINER A2s for external sale has been fully reserved by customers. This allocation is subject to further increase depending on market conditions.
|
•
|
HPC/AI:
|
o
|
Discussions are ongoing with multiple development partners and potential end users for selected sites.
|
o
|
Bitdeer AI cloud services deployed an early batch of NVIDIA H200 in the Company’s Tier 3 datacenter.
|
o
|
Expanded AI cloud services to United States and Holland. AI cloud services are now hosted from Singapore, Canada, United States and Holland.
|
•
|
Hosting:
|
o
|
Client-hosted machines increased by 11,000 units or 2.6 EH/s.
|
•
|
Infrastructure:
|
o
|
Tydal, Norway, 40 MW phase 1 expansion was expected to be ready for use by December 2024. Energization pending regulatory approval.
|
o
|
Rockdale, Texas, USA, 100MW hydro-cooling conversion is on track for phased completion during Q1 2025.
|
o
|
Jigmeling, Bhutan, 500 MW construction is on track with the primary substation expected to be completed by Q1 2025.
|
o
|
1.1 GW of new power capacity is on track to come online in 2025.
|
Metrics
|
Nov 2024
|
Oct 2024
|
Nov 2023
|
Total hash rate under management1 (EH/s)
|
20.7
|
18.0
|
21.1
|
- Proprietary hash rate
|
8.8
|
8.7
|
8.7
|
• Self-mining
|
8.2
|
8.4
|
7.1
|
• Cloud Hash Rate
|
0.2
|
0.3
|
1.6
|
• Delivered but not hashing
|
0.4
|
-
|
-
|
- Hosting
|
11.9
|
9.3
|
12.4
|
Mining machines under management
|
178,000
|
168,000
|
220,000
|
- Self-owned2
|
86,000
|
87,000
|
92,000
|
- Hosted
|
92,000
|
81,000
|
128,000
|
Bitcoins mined (self-mining only)
|
150
|
174
|
403
|
Bitcoins held3
|
443
|
372
|
28
|
•
|
Self-mining refers to cryptocurrency mining for the Company’s own account, which allows it to directly capture the high
appreciation potential of cryptocurrency.
|
•
|
Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The
Cloud Hash Rate stated above reflects the contracted hash rate with customers at month-end. However, throughout the month, the Cloud Hash Rate may transition to Self-mining hash rate if customers opt to not make their monthly
electricity payments for various reasons.
|
•
|
Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services
for efficient cryptocurrency mining.
|
•
|
Demolition work completed.
|
•
|
Cooling system will be delivered and installed in phases from Q4 2024 to Q1 2025.
|
•
|
Due to supply chain delays from the US dock workers strike in early October, the expected phased energization timeline is expected to occur one month later, now between January and March 2025.
|
•
|
Buildings and groundwork completed, along with the construction of the transformer foundation and housing.
|
•
|
Orders for transformer and electrical equipment have been placed, with delivery and installation currently in progress. Additionally, the procurement and delivery of containers and hydro-cooling systems are underway, and drainage
systems construction is ongoing.
|
•
|
Construction of the substation completed.
|
•
|
Tydal, Norway Phase 1 of 40 MW Expansion had been expected to be ready for use by December 2024 but could be delayed for a few months due to regulatory approval application issues, which are now under close monitoring of the management team. Energization of the full 175 MW site is reasonably expected to be no later than mid-2025.
|
•
|
Substation conceptual design is completed and long lead-time electrical equipment for the substation have been ordered.
|
•
|
Engineering, Procurement, and Construction (EPC) contractor has been selected for the substation construction.
|
•
|
Civil work is ongoing, with the majority expected to be completed by the end of Q4 2024 or Q1 2025.
|
•
|
Building design is completed, and construction is anticipated to begin in Q4 2024, earlier than expected.
|
•
|
Estimated energization timeline remains on track for mid-to-late 2025.
|
•
|
Civil work is finished. Construction of transformer and container foundations is in progress and will be completed in phases, with the last phase expected by the end of February 2025.
|
•
|
132kv/140MW and 220kv/360MW substation designs are completed with construction anticipated to be ready by the end of Q1 2025.
|
•
|
Orders for the procurement of transformers and electrical equipment have been placed, with delivery and installation work to be completed in phases over the next two quarters.
|
•
|
Procurement and delivery of containers and hydro-cooling systems are in progress, with completion in phases by the end of Q1 2025.
|
Site / Location
|
Capacity (MW)
|
Status
|
Timing4
|
Electrical capacity
|
|||
- Rockdale, Texas
|
563
|
Online
|
Completed
|
- Knoxville, Tennessee
|
86
|
Online
|
Completed
|
- Wenatchee, Washington
|
13
|
Online
|
Completed
|
- Molde, Norway
|
84
|
Online
|
Completed
|
- Tydal, Norway
|
50
|
Online
|
Completed
|
- Gedu, Bhutan
|
100
|
Online
|
Completed
|
Total electrical capacity
|
8955
|
||
Pipeline capacity
|
|||
- Tydal, Norway Phase 1
|
40
|
In progress
|
Pending Regulatory Approval
|
- Tydal, Norway Phase 2
|
135
|
In progress
|
Mid 2025
|
- Massillon, Ohio
|
221
|
In progress
|
Mid-to-late 2025
|
- Clarington, Ohio Phase 1
|
266
|
In progress
|
Q3 2025
|
- Clarington, Ohio Phase 2
|
304
|
Pending approval
|
Estimate 2026
|
- Jigmeling, Bhutan
|
500
|
In progress
|
Mid-to-late 2025
|
- Rockdale, Texas
|
179
|
In planning
|
Estimate 2026
|
Total pipeline capacity
|
1,645
|
||
Total global electrical capacity
|
2,540
|
•
|