株探米国株
英語
エドガーで原本を確認する
6-K 1 tm2416946d3_6k.htm FORM 6-K

 

 

 

UNITED STATES 

SECURITIES AND EXCHANGE COMMISSION 

Washington, D.C. 20549

 

Form 6-K

 

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE
SECURITIES EXCHANGE ACT OF 1934

 

For the month of August, 2024

 

Commission File Number 001-13422

 

AGNICO EAGLE MINES LIMITED

(Translation of registrant’s name into English)

 

145 King Street East, Suite 400, Toronto, Ontario M5C 2Y7

(Address of principal executive office)

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

Form 20-F ¨     Form 40-F x

 

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101 (b)( 1): ¨

 

Note: Regulation S-T Rule 101 (b)( 1) only permits the submission in paper of a Form 6-K if submitted solely to provide an attached annual report to security holders.

 

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101 (b)(7): ¨

 

Note: Regulation S-T Rule 101(b)(7) only permits the submission in paper of a Form 6-K if submitted to furnish a report or other document that the registrant foreign private issuer must furnish and make public under the laws of the jurisdiction in which the registrant is incorporated, domiciled or legally organized (the registrant’s “home country”), or under the rules of the home country exchange on which the registrant’s securities are traded, as long as the report or other document is not a press release, is not required to be and has not been distributed to the registrant’s security holders, and, if discussing a material event, has already been the subject of a Form 6-K submission or other Commission filing on EDGAR.

 

Indicate by check mark whether the registrant by furnishing the information contained in this Form is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the Securities Exchange Act of 1934. Yes ¨   No x

 

If “Yes” is marked, indicate below the file number assigned to the registrant in connection with Rule 12g3-2(b): 82-____________.

 

 


 

EXHIBITS

 

Exhibit No. Exhibit Description
99.1 Press Release dated July 31, 2024 announcing the Corporation’s second quarter results

 

SIGNATURES

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

AGNICO EAGLE MINES LIMITED
(Registrant)
   
Date: 08/02/2024 By: /s/ Chris Vollmershausen
  Chris Vollmershausen 
  Executive Vice-President, Legal, General
    Counsel & Corporate Secretary

 

2

EX-99.1 2 tm2416946d3_ex99-1.htm EXHIBIT 99.1

Exhibit 99.1

 

 

Stock Symbol: AEM (NYSE and TSX)

 

For further information: Investor Relations
  (416) 947-1212

 

(All amounts expressed in U.S. dollars unless otherwise noted)

 

AGNICO EAGLE REPORTS SECOND QUARTER 2024 RESULTS – THIRD CONSECUTIVE QUARTER OF RECORD FREE CASH FLOW UNDERPINNED BY CONSISTENT, STRONG OPERATIONAL AND COST PERFORMANCE; UPPER BEAVER PROJECT STUDY SHOWS SOLID RISK-ADJUSTED RETURNS

 

Toronto (July 31, 2024) – Agnico Eagle Mines Limited (NYSE:AEM, TSX:AEM) ("Agnico Eagle" or the "Company") today reported financial and operating results for the second quarter of 2024.

 

"We continue to deliver strong and reliable operational results which, combined with higher gold prices, drove record operating margin and free cash flow for the third consecutive quarter. As a result of the excellent performance of our operations through the first half of 2024, we are highly confident we will achieve our full year production and cost guidance," said Ammar Al-Joundi, Agnico Eagle's President and Chief Executive Officer. "We generated over half of a billion dollars of free cash flow in the second quarter, supporting a significant strengthening of our balance sheet and increased returns to shareholders. We continue to take a measured approach advancing key pipeline projects that show strong risk-adjusted returns, such as the Detour Lake underground and Upper Beaver projects. Our focus remains on capital discipline and cost control to ensure that the benefits of higher gold prices accrue to our shareholders through strengthening our financial position and increasing shareholder returns," added Mr. Al-Joundi.

 

Second quarter 2024 highlights:

 

Strong quarterly gold production – Payable gold production1 was 895,838 ounces at production costs per ounce of $862, total cash costs per ounce2 of $870 and all-in sustaining costs ("AISC") per ounce2 of $1,169. Gold production was led by strong production at Canadian Malartic, LaRonde and Fosterville

 

 

1 Payable production of a mineral means the quantity of a mineral produced during a period contained in products that have been or will be sold by the Company whether such products are shipped during the period or held as inventory at the end of the period.

2 Total cash costs per ounce and AISC per ounce are non-GAAP ratios that are not standardized financial measures under IFRS and, in this news release, unless otherwise specified, are reported on (i) a per ounce of gold production basis, and (ii) a by-product basis. For a description of the composition and usefulness of these non-GAAP measures and reconciliations of total cash costs per ounce and AISC per ounce to production costs on both a by-product and a co-product basis, see "Note Regarding Certain Measures of Performance" below.

 

1


 

Record quarterly adjusted net income3 – The Company reported quarterly net income of $472.0 million or $0.95 per share and adjusted net income of $535.3 million or $1.07 per share

 

Record quarterly cash provided by operating activities and free cash flow – The Company generated record cash provided by operating activities of $961.3 million or $1.92 per share ($986.2 million or $1.97 per share before changes in non-cash working capital balances4) and free cash flow4 of $557.2 million or $1.12 per share ($582.2 million or $1.17 per share before changes in non-cash working capital balances4)

 

Strengthening investment grade balance sheet and financial flexibility – The Company increased its cash position by $397.4 million to $922.0 million and significantly reduced net debt as at June 30, 2024. Subsequent to quarter-end, the Company repaid the $100.0 million 5.02% Series B senior notes at maturity and repaid $150.0 million of the $600.0 million unsecured term loan facility drawn in 2023

 

2024 gold production and cost guidance reiterated – Full year expected payable gold production remains unchanged at approximately 3.35 to 3.55 million ounces in 2024, with total cash costs per ounce and AISC per ounce in 2024 unchanged at $875 to $925 and $1,200 to $1,250, respectively. Total capital expenditures (excluding capitalized exploration) for 2024 are still estimated to be between $1.6 billion to $1.7 billion. Capitalized exploration is now expected to be approximately $187 million for the full year 2024. Further details are set out in the "2024 Guidance" section below

 

Update on key value drivers and pipeline projects

 

Approval of measured investments over next three years to further evaluate and de-risk the Detour Lake underground and Upper Beaver projects – Based on internal studies indicating solid risk-adjusted returns for the Detour Lake underground and Upper Beaver projects5, the Company has adopted a measured approach to advance these projects, approving $100.0 million and $200.0 million investments, respectively, over approximately three years. At Detour Lake, a 2.0-kilometre exploration ramp is expected to be developed to a depth of 270 metres to collect a bulk sample and to facilitate infill and expansion drilling of the current underground mineral resource. At Upper Beaver, an exploration ramp and an exploration shaft are expected to be developed to a depth of 250 metres and 760 metres, respectively, to establish underground drilling platforms and collect bulk samples

 

Detour Lake – In June 2024, the Company released the results of a technical study reflecting the potential for a concurrent underground operation at Detour Lake that would accelerate access to higher grade ore and increase annual production to approximately one million ounces for 14 years starting in 2030 (see the Company's news release dated June 19, 2024). In the second quarter of 2024, with the replacement of the defective grinding media at the SAG mill and record quarterly mill availability of 93.0%, mill throughput improved to 74,637 tonnes per day ("tpd") and is expected to reach the target rate of 76,700 tpd by the end of 2024

 

 

3 Adjusted net income and adjusted net income per share are non-GAAP measures or ratios that are not standardized financial measures under IFRS. For a description of the composition and usefulness of these non-GAAP measures and a reconciliation to net income see "Note Regarding Certain Measures of Performance" below.

4 Cash provided by operating activities before changes in non-cash working capital balances, free cash flow and free cash flow before changes in non-cash working capital balances and their related per share measures are non-GAAP measures or ratios that are not standardized financial measures under IFRS. For a description of the composition and usefulness of these non-GAAP measures and a reconciliation to cash provided by operating activities see "Note Regarding Certain Measures of Performance" below.

5 The forecast parameters surrounding the technical study for the Detour Lake underground project and the internal evaluation for the Upper Beaver project were based on a preliminary economic assessment, which is preliminary in nature and includes inferred mineral resources. For further detail, refer to the Company's news release dated June 19, 2024 for the Detour Lake underground project and the Update on Key Value Drivers and Pipeline Projects section set our below for the Upper Beaver project.

 

2


 

Upper Beaver – A positive internal evaluation was completed in June 2024 for a standalone mine and mill scenario at Upper Beaver. Based on this evaluation, the Company believes Upper Beaver has the potential to produce an annual average of approximately 210,000 ounces of gold and 3,600 tonnes of copper, with initial production possible as early as 2030. Over an expected 13-year mine life, total payable gold and copper production is expected to be approximately 2.8 million ounces and 46,300 tonnes, respectively. Estimated total cash costs per ounce on a by-product basis and AISC per ounce on a by-product basis are expected to be approximately $592 and $733, respectively. In addition, the project has the potential to unlock significant exploration potential at depth and within satellite deposits in the Company's Kirkland Lake camp

 

Odyssey mine at Canadian Malartic – At Odyssey South, record quarterly mining rates and gold production were achieved at approximately 3,750 tpd and 22,300 ounces of gold, respectively. In the second quarter of 2024, ramp development continued to exceed the Company's target, reaching the third production level at East Gouldie at a depth of 832 metres as at June 30, 2024. Shaft sinking advanced at an average rate of 2.5 metres per day and reached a depth of 680 metres as at June 30, 2024. Surface construction is progressing as planned, with a focus on the main hoist building, phase two of the paste plant and the operations complex

 

Approval of a supplemental exploration budget of $50.0 million – The Company's exploration program returned positive results in the first half of 2024 at Canadian Malartic, Detour Lake and Hope Bay, showing excellent potential to identify additional mineral resources. These results support increased budgets approved by the Company for the second half of 2024.

 

East Gouldie at Odyssey mine – Recent exploration drilling continued to return good results in the eastern and western extensions of the East Gouldie deposit including 4.5 grams per tonne ("g/t") gold over 6.5 metres at 1,571 metres depth approximately 770 metres east of the current mineral reserves and 2.5 g/t gold over 30.0 metres at 1,473 metres depth and 85 metres west of the current mineral reserves. The results from the ongoing exploration program are anticipated to have a positive impact on the mineral resource estimate at year-end 2024

 

Detour Lake underground – Infill drilling into the high-grade corridor in the West Pit zone continued to confirm the higher grades and mineralized structure amenable to underground mining. Highlights include 4.0 g/t gold over 22.3 metres at 413 metres depth and 4.4 g/t gold over 30.1 metres at 550 metres depth. Near the proposed exploration ramp, highlights include 20.6 g/t gold over 5.5 metres at 280 metres depth and 4.7 g/t gold over 15.6 metres at 313 metres depth

 

Madrid at Hope Bay – Exploration drilling during the second quarter of 2024 totalled 35,400 metres and continued to return strong results from infill drilling north of the Patch 7 mineral resources, including 17.0 g/t gold over 25.8 metres at 419 metres depth, 7.2 g/t gold over 8.1 metres at 559 metres depth and 5.3 g/t gold over 18.0 metres at 278 metres depth, further confirming the greater thicknesses and higher gold grades in this area compared to the rest of the Madrid deposit

 

Reconciliation Action Plan and 2023 Climate Action Report published – On July 10, 2024, the Company released its first Reconciliation Action Plan, reinforcing its commitment to reconciliation with Indigenous Peoples and communities. In addition, on July 31, 2024, the Company released its 2023 Climate Action Report. In line with the recommendations of the Task Force on Climate-related Financial Disclosures and Towards Sustainable Mining Climate Change protocol, the 2023 Climate Action Report outlines how the Company is addressing climate change risks and opportunities

 

Continued focus on shareholder returns – In the second quarter of 2024, the board of directors declared a quarterly dividend of $0.40 per share. In the second quarter of 2024, the Company also repurchased 763,043 common shares at an average share price of $65.53 for an aggregate of $50.0 million through its normal course issuer bid ("NCIB"), which was renewed in May 2024

 

3


 

Second Quarter 2024 Results Conference Call and Webcast Tomorrow

 

Agnico Eagle's senior management will host a conference call on Thursday, August 1, 2024 at 11:00 AM (E.D.T.) to discuss the Company's financial and operating results.

 

Via Webcast:

 

To listen to the live webcast of the conference call, you may register on the Company website at www.agnicoeagle.com, or directly via the link here.

 

Via Phone:

 

To join the conference call by phone, please dial 416.764.8659 or toll-free 1.888.664.6392 to be entered into the call by an operator. To ensure your participation, please call approximately five minutes prior to the scheduled start of the call.

 

To join the conference call by phone without operator assistance, you may register your phone number here 30 minutes prior to the scheduled start of the call to receive an instant automated call back.

 

Replay Archive:

 

Please dial 416.764.8677 or toll-free 1.888.390.0541, access code 576159#. The conference call replay will expire on September 1, 2024.

 

The webcast, along with presentation slides, will be archived for 180 days on the Company's website.

 

Second Quarter 2024 Production and Cost Results

 

Production and Cost Results Summary*

 

    Three Months Ended
June 30,
    Six Months Ended
June 30,
 
    2024     2023     2024     2023  
Gold production (ounces)     895,838       873,204       1,774,490       1,686,017  
Gold sales (ounces)     874,230       858,848       1,753,293       1,646,406  
Production costs per ounce   $ 862     $ 851     $ 877     $ 828  
Total cash costs per ounce   $ 870     $ 840     $ 885     $ 836  
AISC per ounce   $ 1,169     $ 1,150     $ 1,179     $ 1,138  

 

* Production and Cost Results Summary reflects Agnico Eagle's 50% interest in Canadian Malartic up to and including March 30, 2023 and 100% thereafter.

 

Gold Production

 

Second Quarter of 2024 – Gold production increased when compared to the prior-year period primarily due to higher production from Meadowbank and Macassa, partially offset by lower production at Fosterville

 

First Six Months of 2024 – Gold production increased when compared to the prior-year period as a result of the additional production from the acquisition of the remaining 50% of Canadian Malartic, contribution from Odyssey in the current year and increased production from Meadowbank, partially offset by lower production at Fosterville

 

4


 

Production Costs per Ounce

 

Second Quarter and First Six Months of 2024 – Total production costs per ounce increased when compared to the prior-year periods primarily due to higher royalties mainly arising from higher gold prices and higher production costs at Canadian Malartic related to underground mining operations, partially offset by higher gold production during the period

 

Total Cash Costs per Ounce

 

Second Quarter and First Six Months of 2024 – Total cash costs per ounce increased when compared to the prior-year periods primarily due to the reasons described above for the increase in production costs per ounce combined with the impact of lower gold grades at Fosterville, partially offset by higher gold production during the period

 

AISC per Ounce

 

Second Quarter of 2024 – AISC per ounce increased when compared to the prior-year period due to the factors causing higher total cash costs per ounce, partially offset by higher production and slightly lower sustaining capital expenditures during the period

 

First Six Months of 2024 – AISC per ounce increased when compared to the prior-year period due to the factors causing higher total cash costs per ounce and higher sustaining capital expenditures, partially offset by higher gold production during the period

 

5


 

Second Quarter 2024 Financial Results

 

Financial Results Summary

 

    Three Months Ended
June 30,
    Six Months Ended
June 30,
 
    2024     20236     2024     20236  
Realized gold price ($/ounce)   $ 2,342     $ 1,975     $ 2,202     $ 1,935  
Net income ($ millions)   $ 472.0     $ 323.7     $ 819.2     $ 2,140.6  
Adjusted net income ($ millions)   $ 535.3     $ 319.3     $ 912.7     $ 590.5  
EBITDA ($ millions)   $ 1,123.1     $ 883.4     $ 2,005.6     $ 3,156.3  
Adjusted EBITDA ($ millions)9   $ 1,176.2     $ 885.2     $ 2,105.5     $ 1,625.6  
Cash provided by operating activities ($ millions)   $ 961.3     $ 722.0     $ 1,744.5     $ 1,371.6  
Cash provided by operating activities before changes in non-cash working capital balances ($ millions)   $ 986.2     $ 693.0     $ 1,763.3     $ 1,301.8  
Capital expenditures   $ 407.3     $ 416.0     $ 779.3     $ 757.8  
Free cash flow ($ millions)   $ 557.2     $ 298.4     $ 952.8     $ 563.1  
Free cash flow before changes in non-cash working capital balances ($ millions)   $ 582.2     $ 269.4     $ 971.6     $ 493.3  
                                 
Net income per share (basic)   $ 0.95     $ 0.66     $ 1.64     $ 4.45  
Adjusted net income per share (basic)   $ 1.07     $ 0.65     $ 1.83     $ 1.23  
Cash provided by operating activities per share (basic)   $ 1.92     $ 1.46     $ 3.50     $ 2.85  
Cash provided by operating activities before changes in non-cash working capital balances per share (basic)   $ 1.97     $ 1.40     $ 3.54     $ 2.70  
Free cash flow per share (basic)   $ 1.12     $ 0.60     $ 1.91     $ 1.17  
Free cash flow before changes in non-cash working capital balances per share (basic)   $ 1.17     $ 0.55     $ 1.95     $ 1.02  

 

Net Income

 

Second Quarter of 2024

 

Net income was $472.0 million ($0.95 per share). This result includes the following items (net of tax): non-recurring tax adjustments and foreign currency translation losses on deferred tax liabilities of $25.7 million ($0.05 per share), derivative losses on financial instruments of $14.4 million ($0.03 per share), net asset disposals losses of $11.5 million ($0.02 per share) and foreign exchange and other losses of $11.7 million ($0.02 per share)

 

Excluding the above items results in adjusted net income of $535.3 million or $1.07 per share

 

Included in net income and not adjusted above, is a non-cash stock option expense of $2.1 million (less than $0.01 per share)

 

Net income of $472.0 million in the second quarter of 2024 increased compared to net income of $323.7 million in the prior-year period primarily due to stronger mine operating margins11 resulting from higher realized gold prices and higher sales volumes, partially offset by losses on derivative financial instruments in the current period, and higher income and mining tax expenses

 

 

6 Certain previously reported line items have been restated to reflect the final purchase price allocation related to the acquisition of the Canadian assets of Yamana Gold Inc. (the "Yamana Transaction") including the 50% of Canadian Malartic that the Company did not own.

7 Realized gold price is calculated as gold revenues from mining operations divided by the number of ounces sold.

8 For the first quarter of 2023, includes a $1.5 billion revaluation gain on the 50% interest the Company owned in Canadian Malartic prior to the Yamana Transaction on March 31, 2023.

9 "EBITDA" means earnings before interest, taxes, depreciation, and amortization. EBITDA and adjusted EBITDA are non-GAAP measures or ratios that are not standardized financial measures under IFRS. For a description of the composition and usefulness of these non-GAAP measures and a reconciliation to net income see "Note Regarding Certain Measures of Performance" below.

10 Includes capitalized exploration.

11 Operating margin is a non-GAAP measure that is not a standardized measure under IFRS. For a description of the composition and usefulness of this non-GAAP measure and a reconciliation to net income see “Note Regarding Certain Measures of Performance” below.

 

6


 

First Six Months of 2024 – Net income of $819.2 million decreased compared to the prior-year period primarily due to a remeasurement gain at Canadian Malartic in the prior period resulting from the application of purchase accounting relating to a business combination attained in stages, which requires the remeasurement of the Company's previously held 50% interest in Canadian Malartic to fair value, partially offset by higher realized gold prices and higher sales volumes

 

Adjusted EBITDA

 

Second Quarter of 2024 – Adjusted EBITDA increased when compared to the prior-year period primarily due to stronger mine operating margins from higher realized gold prices and higher sales volumes

 

First Six Months of 2024 – Adjusted EBITDA increased when compared to the prior-year period primarily due to the reasons set out above for net income and as a result of the acquisition of the remaining 50% of Canadian Malartic

 

Cash Provided by Operating Activities

 

Second Quarter and First Six Months of 2024 – Cash provided by operating activities and cash provided by operating activities before changes in non-cash working capital balances increased when compared to the prior-year periods primarily due to the reasons described above related to the increases in adjusted EBITDA

 

Free Cash Flow Before Changes in Non-cash Working Capital Balances

 

Second Quarter and First Six Months of 2024 – Free cash flow before changes in non-cash working capital balances was a record for the third consecutive quarter and increased when compared to the prior-year periods due to the reasons described above related to cash provided by operating activities, as well as lower additions to property, plant and mine development

 

7


 

Capital Expenditures

 

In the second quarter of 2024, capital expenditures were $362.4 million and capitalized exploration expenditures were $44.9 million, for a total of $407.3 million. Expected capital expenditures (excluding capitalized exploration) remain in line with guidance for the full year 2024. As a result of the supplemental exploration budget approved of $50.0 million and the approval of the exploration ramp construction at Detour Lake and the exploration ramp and exploration shaft construction at Upper Beaver, capitalized exploration is expected to increase to approximately $186.8 million for the full year 2024. Further details are set out in the "2024 Guidance" section below.

 

The following table sets out a summary of capital expenditures (including sustaining capital expenditures12 and development capital expenditures12) and capitalized exploration in the second quarter of 2024 and the first six months of 2024.

 

 

12 Sustaining capital expenditures and development capital expenditures are non-GAAP measures that are not standardized financial measures under IFRS. For a discussion of the composition and usefulness of these non-GAAP measures and a reconciliation to additions to property, plant and mine development as set out in the consolidated statements of cash flows, see "Note Regarding Certain Measures of Performance" below.

 

8


 

Summary of Capital Expenditures                        
($ thousands)                        
      Capital Expenditures*       Capitalized Exploration  
    Three Months
Ended
    Six Months
Ended
    Three Months
Ended
    Six Months
Ended
 
    Jun 30, 2024     Jun 30, 2024     Jun 30, 2024     Jun 30, 2024  
Sustaining Capital Expenditures                                
LaRonde   $ 20,899     $ 43,823     $ 557       876  
Canadian Malartic     28,053       55,098              
Goldex     11,354       23,407       1,045       1,783  
Detour Lake     61,971       111,609              
Macassa     6,058       16,189       408       808  
Meliadine     16,083       33,948       2,490       3,827  
Meadowbank     21,560       41,502              
Fosterville     7,306       12,789              
Kittila     18,212       34,276       415       865  
Pinos Altos     6,102       11,091       617       920  
La India           22              
Other     1,940       2,269       270       845  
Total Sustaining Capital Expenditures   $ 199,538     $ 386,023     $ 5,802     $ 9,924  
                                 
Development Capital Expenditures                                
LaRonde   $ 20,637     $ 44,726     $        
Canadian Malartic     43,199       79,204       874       2,192  
Goldex     2,925       7,056              
Detour Lake     31,315       69,074       9,547       17,099  
Macassa     22,312       34,458       9,386       17,704  
Meliadine     18,849       37,094       2,720       6,806  
Meadowbank           (27 )            
Fosterville     9,186       18,614       3,342       6,966  
Kittila     1,288       2,196       2,428       4,559  
Pinos Altos     806       1,452             4  
San Nicolás project     6,284       11,655              
Other     6,051       8,016       10,813       14,525  
Total Development Capital Expenditures   $ 162,852     $ 313,518     $ 39,110     $ 69,855  
Total Capital Expenditures   $ 362,390     $ 699,541     $ 44,912     $ 79,779  

 

* Excludes capitalized exploration

 

2024 Guidance

 

Production and Cost Guidance

 

Full year guidance remains unchanged at approximately 3.35 to 3.55 million ounces of gold, total cash costs per ounce of $875 to $925 and AISC per ounce of $1,200 to $1,250.

 

Capital Expenditure Guidance

 

Total expected capital expenditures (excluding capitalized exploration) for 2024 are still estimated to be between $1.6 billion to $1.7 billion.

 

9


 

Exploration Guidance

 

The Company's exploration and corporate development expense for 2024 is now expected to be approximately $271.4 million (compared to $230.0 million in the prior guidance). Based on positive exploration results in the first half of 2024 at Canadian Malartic, Detour Lake and Hope Bay, the Company has approved a supplemental budget of $50.0 million ($41.4 million expensed exploration and $8.6 million capitalized exploration). The supplemental exploration budget includes $16.5 million at Canadian Malartic for 84,500 metres of drilling, $10.9 million at Detour Lake for 55,000 metres of drilling (of which $8.6 million will be non-sustaining capitalized exploration expenditures) and $22.6 million at Hope Bay for 62,000 metres of drilling.

 

The Company's capitalized exploration expenditures are now expected to be approximately $186.8 million (compared to $110.0 million in the prior guidance). To further study and de-risk the Detour Lake underground and Upper Beaver projects, the Company has approved $100.0 million and $200.0 million investments, respectively, over approximately three years. At Detour Lake, approximately $19.6 million is forecast to be spent in 2024 related to the construction of surface facilities and site preparation. At Upper Beaver, approximately $50.0 million is forecast to be spent in 2024 related to the construction of surface facilities, site preparation and the excavation of the shaft collar (of which $15.0 million was spent in the first half of 2024).

 

The breakdown of the incremental budget approved in exploration expense and capitalized exploration expenditures is set out in the table below.

 

Estimated 2024 Mid-Point Exploration and Corporate Development Expense and 2024 Capitalized Exploration Expenditures

 

      Exploration and
Corporate
    Capitalized Exploration  
($ thousands)     Development Expense     Sustaining     Non-Sustaining  
Prior Guidance   $ 230,000     $ 16,500     $ 92,100  
Incremental exploration expenditures:                        
Canadian Malartic     16,500              
Detour Lake     2,300             28,200  
Upper Beaver                 50,000  
Hope Bay     22,600              
Guidance   $ 271,400     $ 16,500     $ 170,300  

 

Depreciation Guidance

 

Depreciation and amortization expense in 2024 is now expected to be at the lower end of the guidance range of $1.56 to $1.61 billion.

 

Record Cash Flow Generation Continues to Enhance Investment Grade Balance Sheet Alongside Continued Commitment to Shareholder Returns

 

Cash and cash equivalents increased by $397.4 million when compared to the prior quarter primarily due to higher cash provided by operating activities as a result of higher revenues from higher realized gold prices and higher sales volumes.

 

10


 

As at June 30, 2024, the Company's long-term debt was $1,841.7 million, consistent with the prior quarter. No amounts were outstanding under the Company's unsecured revolving bank credit facility as at June 30, 2024, and available liquidity remained at approximately $2.0 billion, not including the uncommitted $1.0 billion accordion feature.

 

The following table sets out the calculation of net debt13, which decreased by $396.7 million when compared to the prior quarter primarily as a result of higher cash and cash equivalents.

 

Net Debt Summary                
($ millions)                
      As at       As at  
      Jun 30, 2024       Mar 31, 2024  
Current portion of long-term debt   $ 740.0     $ 100.0  
Non-current portion of long-term debt     1,101.7       1,741.0  
Long-term debt   $ 1,841.7     $ 1,841.0  
Less: cash and cash equivalents     (922.0 )     (524.6 )
Net debt   $ 919.7     $ 1,316.4  

 

Subsequent to June 30, 2024, the Company completed two debt repayments. On July 24, 2024, $100.0 million was repaid with cash on hand on the 2012 Series B 5.02% Senior Notes on maturity and on July 31, 2024, $150.0 million was repaid with cash on hand of the $600.0 million outstanding on the term loan facility. The remaining $450.0 million of indebtedness under the term loan facility is due and payable by April 21, 2025.

 

In order to maintain financial flexibility, and consistent with past practice, the Company filed a new base shelf prospectus in the second quarter of 2024. The Company has no present intention to offer securities pursuant to the base shelf prospectus and the notice set out in this paragraph does not constitute an offer of any securities for sale or an offer to sell or the solicitation of an offer to buy any securities.

 

Hedges

 

Approximately 73% of the Company's remaining estimated Canadian dollar exposure for 2024 is hedged at an average floor price providing protection above 1.34 C$/US$. Approximately 27% of the Company's remaining estimated Euro exposure for 2024 is hedged at an average floor price providing protection below 1.10 US$/EUR. Approximately 62% of the Company's remaining Australian dollar exposure for 2024 is hedged at an average floor price providing protection above 1.46 A$/US$. Approximately 21% of the Company's remaining estimated Mexican peso exposure for 2024 is hedged at an average floor price providing protection above 18.00 MXP/US$. The Company's full year 2024 cost guidance is based on assumed exchange rates of 1.34 C$/US$, 1.10 US$/EUR, 1.45 A$/US$ and 16.50 MXP/US$.

 

With the 2024 sealift underway at the Company’s Nunavut operations, approximately 66% of the total diesel purchases have been completed, with initial deliveries in progress. Factoring in these purchases and anticipated deliveries, approximately 40% of the Company's remaining estimated diesel exposure for 2024 is hedged at an average price of $0.76 per litre (excluding transportation and taxes), which is expected to reduce the Company's exposure to diesel price volatility in 2024. The Company's full year 2024 cost guidance is based on an assumed diesel price of $0.80 per litre (excluding transportation and taxes).

 

 

13 Net debt is a non-GAAP measure that is not a standardized financial measure under IFRS. For a description of the composition and usefulness of this non-GAAP measure and a reconciliation to long-term debt, see "Note Regarding Certain Measures of Performance" below.

 

11


 

The Company will continue to monitor market conditions and anticipates continuing to opportunistically add to its operating currency and diesel hedges to strategically support its key input costs. Hedging positions are not factored into 2024 or future guidance.

 

Shareholder Returns

 

Dividend Record and Payment Dates for the Third Quarter of 2024

 

Agnico Eagle's Board of Directors has declared a quarterly cash dividend of $0.40 per common share, payable on September 16, 2024 to shareholders of record as of August 30, 2024. Agnico Eagle has declared a cash dividend every year since 1983.

 

Expected Dividend Record and Payment Dates for the 2024 Fiscal Year

 

Record Date   Payment Date
March 1, 2024*   March 15, 2024*
May 31, 2024*   June 14, 2024*
August 30, 2024**   September 16, 2024**
November 29, 2024   December 16, 2024

 

*Paid

**Declared

 

Dividend Reinvestment Plan

 

Subsequent to the end of the second quarter of 2024, the Company's board of directors approved an amendment to the terms of its dividend reinvestment plan (the "DRIP") to provide the Company with the flexibility to adjust the discount provided under the DRIP to between no discount (0%) and 5%. The changes remain subject to pre-clearance by the Toronto Stock Exchange (the "TSX"). For the dividend payable on September 16, 2024 to shareholders of record as of August 30, 2024, provided the Company has received TSX pre-clearance for the amendment, the Company has determined that the discount provided for under the DRIP will be 1%. If the discount is altered or eliminated by the Company in the future, the Company will include information regarding the change in discount from such level in a news release prior to the effectiveness of the change.

 

For a copy of the amended and restated DRIP, which will be posted on receipt of TSX pre-clearance of the amendment, and for additional information on the Company's DRIP see: Dividend Reinvestment Plan

 

International Dividend Currency Exchange

 

For information on the Company's international dividend currency exchange program, please contact Computershare Trust Company of Canada by phone at 1.800.564.6253 or online at www.investorcentre.com or www.computershare.com/investor.

 

Normal Course Issuer Bid

 

In addition to the quarterly dividend, the Company believes that its NCIB is a flexible and complementary tool that is part of the Company's overall capital allocation program and that generates value for shareholders. The Company received approval from the TSX to renew its NCIB in May 2024, allowing the Company to purchase up to $500.0 million of its common shares, subject to a maximum of 5% of its issued and outstanding common shares. Purchases under the NCIB may continue for up to one year from the commencement day on May 4, 2024. In the second quarter of 2024, the Company repurchased 763,043 common shares for an aggregate of $50.0 million through the NCIB, totalling 1,138,043 common shares repurchased for an aggregate of $69.9 million in the first six months of 2024.

 

12


 

Environment, Social and Governance Highlights

 

Reconciliation Action Plan

 

On July 10, 2024, the Company released its first Reconciliation Action Plan, reinforcing its commitment to reconciliation with Indigenous Peoples and communities. To the Company's knowledge, it is the first mining company in Canada to publish a reconciliation action plan.

 

The Company's reconciliation efforts, which began in Canada, have now expanded globally with many of its operations and offices situated on the traditional territories of different Indigenous Peoples. Agnico Eagleʹs commitment to reconciliation with Indigenous communities is built on three fundamental principles that have shaped the Company for over 65 years: (i) doing what's right, (ii) respecting the rights of all individuals and groups, and (iii) creating value for stakeholders. These principles are reflected in the Reconciliation Action Plan, which was developed in collaboration with Indigenous communities and following consultations with over 250 employees, stakeholders and rights holders.

 

Organized into seven pillars that form the basis for the Company's actions, the Reconciliation Action Plan aligns with the United Nations Declaration on the Rights of Indigenous People and integrates the Company's existing Indigenous programs and initiatives into a central and comprehensive strategy aimed at delivering tangible benefits for Indigenous Peoples. It complements and strengthens the Company's ongoing efforts aimed at contributing to the economic, social and emotional well-being of Indigenous Peoples and communities.

 

Agnico Eagle's Reconciliation Action Plan with Indigenous Peoples is available on the Company's website at www.agnicoeagle.com or can be downloaded directly by clicking here.

 

Dja Dja Wurrung Agreement Signed for Fosterville

 

On May 13, 2024, Agnico Eagle and leaders of the Dja Dja Wurrung People ("Djaara") celebrated the signing of a historic agreement at Fosterville to develop and maintain a long-term relationship based on trust, mutual respect and collaboration. The agreement is called bakaru wayaparrangu, which means "in the middle, we all meet" in the Dja Dja Wurrung language. The agreement is the first to be established in the state of Victoria, Australia between traditional owners and a Company with an active mining operation. The agreement includes measures to increase the Djaara's involvement in activities at Fosterville including training and employment opportunities, fostering business growth and safeguarding the environment, and is complemented by annual financial contributions.

 

2023 Climate Action Report

 

On July 31, 2024, the Company released its 2023 Climate Action Report, which provides an update regarding the Company's 2023 greenhouse gas ("GHG") emissions performance, climate strategy and progress achieved towards climate goals. The report is aligned with the recommendations of the Task Force on Climate-related Financial Disclosures and Towards Sustainable Mining Climate Change protocol, and supplements the Company's 2023 Sustainability Report released in April 2024.

 

Highlights of the 2023 Climate Action Report include:

 

GHG Emissions Targets – Agnico Eagle remains committed to achieving Net-Zero in absolute Scope 1 and Scope 2 carbon emissions by 2050 and maintains its interim carbon reduction target of 30% by 2030 (based on a 2021 baseline)

 

13


 

Industry Leader for GHG Emissions Intensity (Scope 1 and 2) – The Company continues to be a gold industry leader with one of the lowest GHG emissions intensities amongst medium and large gold producers globally. In 2023, the Company's global average GHG emissions intensity was 0.38 tonnes of CO2 equivalent per ounce of gold produced and all 11 active operations outperformed the 2022 industry average14. In 2023, GHG emissions decreased by 3% compared to 2022 and 5% compared to the Company's 2021 baseline

 

Supplier Engagement – Agnico Eagle has improved its Scope 3 methodology to incorporate updated and location-specific emission factors. The Company advanced its supplier engagement program to prioritize decarbonization partnership opportunities with its global supply chain, support improved understanding and increased data availability and to inform decision-making with a view to increasing the Company's climate resilience and reducing Scope 3 emissions

 

Decarbonization Strategy – Agnico Eagle prioritizes investments in technological innovation to support decarbonization focused on (i) energy efficiency, (ii) technology transition, which includes the increased use of battery electric vehicles across multiple operations, and (iii) renewable energy usage, which includes the deployment of cleaner power supplies at operations. Pinos Altos continues to maintain its power purchase agreement to obtain solar-generated electricity, and Kittila entered into a Certificate of Origin agreement to obtain 100% of its grid energy from zero-emission sources

 

Climate Action Corporate Standard – The Company rolled out a Climate Action Corporate Standard establishing a comprehensive process to identify, assess and manage climate-related risks and opportunities across operations, provide guidance for the development of site Climate Action Plans and establish consistent GHG accounting practices for Scope 1, 2 and 3 emissions

 

Climate Transition Assessments – Transition risk assessments have been completed for each operation with the support of subject matter experts. Learnings will be used in building site resilience and in engaging with employees and communities

 

Agnico Eagle's 2023 Climate Action Report is available on the Company's website at www.agnicoeagle.com or can be downloaded directly by clicking here.

 

 

14 Industry average of 0.83 tonnes of CO2 equivalent for Scope 1 and 2 emissions per ounce of gold produced, as per S&P Global Market Intelligence (2022)

 

14


 

Update on Key Value Drivers and Pipeline Projects

 

Highlights on key value drivers, including Upper Beaver, Odyssey, Detour Lake underground, Hope Bay and San Nicolás are set out below. Details on certain mine expansion projects (Detour Lake mill optimization, Meliadine Phase 2 expansion and Amaruq underground) are set out in the applicable operational sections of this news release.

 

Upper Beaver Project

 

An internal evaluation of the Upper Beaver project was completed in June 2024. The study shows solid risk-adjusted economic returns for a standalone mine and mill scenario, based on a 5,000 tpd production rate. The main highlights of this study are set out below.

 

The forecast parameters surrounding the internal evaluation at the Upper Beaver project were based on a preliminary economic assessment, which is preliminary in nature and includes inferred mineral resources that are too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the forecast production amounts or other outcomes will be realized. The basis for the preliminary economic assessment and the qualifications and assumptions made by the Qualified Persons who undertook the preliminary economic assessment are set out in this news release. The impact of the results of the preliminary economic assessment on the results of any pre-feasibility or feasibility study in respect of Upper Beaver are described in the Appendix under "MRMR update for Upper Beaver gold-copper project" and below.

 

Project Description

 

The Upper Beaver gold-copper project is located in the township of Gauthier, in northeastern Ontario, Canada, approximately 25 kilometres to the east of the town of Kirkland Lake. It is hosted in the Kirkland Lake-Larder Lake mining district, within the Company's large Kirkland Lake camp. The district has a continuous history of mineral exploration and mining spanning more than 110 years and with an aggregate of over 42 million ounces of gold produced by various producers. The Company's property portfolio in the Kirkland Lake camp is comprised of approximately 34,000 hectares, is approximately 35 kilometres long by 17 kilometres wide and includes Macassa, the satellite Near Surface and AK deposits, all of the past producing mines along the Main Break and several other past producing mines and several gold deposits, including Upper Beaver, Upper Canada and Anoki-McBean.

 

The Upper Beaver deposit's gold-copper mineralization is mainly hosted in the Upper Beaver alkalic intrusive complex and the surrounding basalts it intruded, and is associated with disseminated pyrite and chalcopyrite, and magnetite-sulphide veining associated with strong magmatic-hydrothermal alteration. The mineralization occurs as elongated tabular bodies that strike northeast, dip steeply northwest and plunge 65 degrees to the northeast. The mineralization has been defined along a 400-metre strike length from surface to a depth of 2,000 metres and it remains open at depth.

 

The mineral reserve and mineral resource estimate at the Upper Beaver project has been updated to June 30, 2024 from the previous estimate at year-end 2023. The new estimate incorporates additional drill results, totalling 226,418 metres in 441 holes, and employs an improved mining concept with updated assumptions and drillhole database to reflect progress in the exploration program, project studies and optimization efforts. In the updated estimate, the mineral reserves have been reclassified as mineral resources that are supported by a positive internal preliminary economic assessment, which includes both indicated mineral resources and inferred mineral resources, that was completed in June 2024. As additional geotechnical fieldwork and metallurgical test work is completed through the remainder of the year, the Company anticipates that most indicated mineral resources will be converted into probable mineral reserves at year-end 2024.

 

A breakdown of the mineral resources used in the internal study is set out in the table below. Additional details on the Upper Beaver mineral resources at June 30, 2024 are set out in the Appendix of this news release. Additional details on the Upper Beaver mineral reserves and mineral resources at December 31, 2023, are set out in the Appendix and in the Company's news release dated February 15, 2024.

 

15


 

    Mineral Resources as at June 30, 2024  
Category   000
Tonnes
    Au
(g/t)
    Au
(000 oz)
    Cu
(%)
    Cu
(000 tonnes)
 
Indicated Mineral Resources (Open Pit)     3,326       1.85       198       0.14       5  
Indicated Mineral Resources (Underground)     27,550       3.66       3,242       0.24       66  
Total Indicated Mineral Resources     30,876       3.47       3,440       0.23       71  
Inferred Mineral Resources (Open Pit)                              
Inferred Mineral Resources (Underground)     2,959       4.13       393       0.36       11  
Total Inferred Mineral Resources     2,959       4.13       393       0.36       11  

 

The mining strategy developed for the Upper Beaver project is to mine the deposit mainly by conventional underground methods, although a small portion (approximately 10% of the mineral resource) will be mined via an open pit. The underground and open pit mines are expected to be developed within the same time frame.

 

Open pit operations will employ conventional methods of drilling, blasting and loading by excavator and wheel loader, with material haulage by truck to the various stockpiles, waste dump or directly to a crusher. Under current scenarios, production from the open pit is expected to occur from 2030 to 2034 at an average rate of approximately 2,000 tpd, of which 500 tpd will be stockpiled for later processing.

 

Current scenarios contemplate underground access through a main decline ramp as well as a shaft that is 1,220 metres deep and six metres in diameter. Four main stations are planned along the shaft, including a loading station at the bottom of the shaft. Ore and waste above 430 metres depth will be hauled to surface by trucks via the ramp. Ore and waste below 430 metres depth will be managed mainly through an ore and waste pass system and skipped to surface via the shaft. The underground mining concept is based on a long hole open stoping method, with sublevels every 30 metres and with stopes to be backfilled with paste and waste rock. The project is expected to use a combination of conventional and automated equipment, similar to what is currently used at the Company's mines in the region. Production from underground, via ramp and shaft, could begin as early as 2030 and ramp-up to an average rate of approximately 4,500 tpd in 2035.

 

The plant is anticipated to use a conventional milling process, including a gravity circuit and a copper flotation circuit, with a design capacity of 5,000 tpd, an average total gold recovery of 95.0% and an average copper recovery of 81.0%. A copper concentrate will be produced with an expected copper content of approximately 20%. Approximately 36% of the gold is expected to report to the copper concentrate and approximately 59% of the gold is expected to be produced in the form of gold doré. Tailings will partly be returned underground as paste fill, with the remainder being disposed on a dry stack tailings storage facility.

 

Located in the Abitibi region, where the Company believes it has a demonstrated competitive advantage, the Company expects the project will benefit from internal technical expertise, local workforce and other regional support and synergies, including procurement and warehousing. The Company believes its strong presence in the region lowers the execution risk for the construction and operation of the project.

 

16


 

The Company believes Upper Beaver has the potential to produce an annual average of approximately 210,000 ounces of gold and 3,600 tonnes of copper, with initial production possible as early as 2030. Over an expected 13-year mine life, total payable gold and copper production are expected to be approximately 2.8 million ounces and 46,300 tonnes, respectively. The total cash costs per ounce on a by-product basis and AISC per ounce on a by-product basis are expected to be approximately $592 and $733, respectively. Initial capital costs are estimated at approximately $0.9 billion. Total sustaining capital expenditures are estimated at approximately $396 million.

 

Using a gold price of $1,900 per ounce, and a C$/US$ foreign exchange rate of 1.34, the Upper Beaver project has an after-tax internal rate of return ("IRR") of 14% and an after-tax NPV (at a 5% discount rate) of approximately $625 million. Using a gold price of $2,300 per ounce, and a C$/US$ foreign exchange rate of 1.34, the Upper Beaver project has an after-tax IRR of 18% and an after-tax NPV (at a 5% discount rate) of approximately $1.01 billion. Additional details on the project are set out in the table below.

 

An agreement with local indigenous communities and environmental permits are in place for the advanced exploration phase of the project, including for the development of an exploration ramp and an exploration shaft and the collection of two bulk samples. Negotiations with indigenous communities are ongoing to establish an agreement for the production phase if a development decision is made. The Company is also advancing environmental impact assessments required for the Federal and Provincial approvals and permits that will be required for the construction and production phases following a development decision.

 

17


 

Upper Beaver Project Summary              
               
(All numbers are approximate)              
Estimated total production         2.8     million ounces of gold
          46.3     thousand tonnes of copper
Average metallurgical recovery         58.5 %   average life of mine for gold doré
          36.5 %   average life of mine for gold in concentrate
          95.0 %   average life of mine total gold recovery
          81.4 %   average life of mine for copper in concentrate
Copper in copper concentrate         20 %    
Payable metal         100 %   gold doré
          96.5 %   gold in concentrate
          94.6 %   copper concentrate
Refining costs       $ 2.00     / oz
        $ 275.00     / tonne of copper concentrate
Average annual gold production   2030     84,000     oz (937kt at 2.98 g/t Au and 0.20% Cu)
    2031     175,000     oz (1,670kt at 3.48 g/t Au and 0.21% Cu)
    2032-2041 (average)     220,000     oz (1,795kt at 4.07 g/t Au and 0.26% Cu)
    2042     191,000     oz (1,475kt at 4.30 g/t Au and 0.28% Cu)
    2043     162,000     oz (1,270kt at 4.24 g/t Au and 0.28% Cu)
Royalty         3.5 %   NSR
Minesite costs per tonne   2030   $ 151     C$/t (includes royalty)
    2031-2043 (average)   $ 114     C$/t (includes royalty)
Average total cash costs on a by-product basis   $ 592     /oz
Average AISC on a by-product basis       $ 733     /oz
Mine life         13     years
Capital Expenditures                
Development capital   H2 2024   $ 35     million
    2025   $ 85     million
    2026   $ 70     million
    2027   $ 100     million
    2028   $ 360     million
    2029   $ 245     million
Sustaining capital   2030   $ 90     million
    2031-2037 (average)   $ 33     million
    2038-2042 (average)   $ 15     million
Total       $ 1,286     million
Reclamation Costs       $ 11     million
Economic Assumptions:                
Gold Price       $ 1,900     /oz
Copper Price       $ 4.00     /lb ($8,819 / tonne)
USD:CAD         1.34      
Effective tax rate         32 %    

 

18


 

Based on the positive result of the internal evaluation and taking a measured approach, the Company has approved a $200.0 million investment over approximately three years to further de-risk the project. With this investment, the Company intends to develop an exploration ramp and an exploration shaft to depths of 160 metres and 760 metres, respectively, to establish underground drilling platforms and to collect bulk samples from the two most representative geological zones of the Upper Beaver deposit. The exploration ramp and exploration shaft will be sized to accommodate the potential production phase and are included in the initial capital expenditures estimate of approximately $0.9 billion.

 

Of the $200.0 million, approximately $35.0 million is forecast to be spent in the second half 2024, related primarily to the upgrade of the access road to the site, site surface preparation, construction of site facilities and excavation of the shaft collar. Preparatory site work commenced in early 2024 and approximately $15.0 million was spent in the first half of 2024. Excavation of the ramp and shaft sinking are expected to start in the second half of 2025.

 

Exploration Upside

 

Exploration results from recent years at Upper Beaver show the potential to increase the mineral resources and to convert inferred mineral resources at depth using underground access via the proposed exploration shaft and other underground infrastructure.

 

In the next stage of development, a bulk sampling program is planned in the two most representative geological zones of the Upper Beaver deposit. The first bulk sample will be taken from the upper level of the deposit, which is dominated by basaltic hosting lithologies, and will have the objective of testing selective mining assumptions in this area of the deposit. The second bulk sample will be taken from the lower level of the deposit, which is dominated by intrusion-suite hosting rocks, with the objective of validating mining parameters and grade variability at greater depth.

 

The Company believes the Upper Beaver project holds significant growth and synergy potential. The main deposit remains open at depth, as demonstrated by historical hole KLUB19-452W1 (presented in the Company's news release dated April 25, 2019), which intersected 7.6 g/t gold and 0.36% copper over 3.4 metres at 1,983 metres depth and 1.2 g/t gold and 1.39% copper over 7.1 metres at 2,041 metres depth, approximately 300 metres down plunge from the nearest mineral resource block.

 

Additionally, multiple intrusions of similar nature to that associated with the emplacement of the Upper Beaver deposit have been identified in the immediate vicinity of the project. These intrusions are undergoing early-stage exploration efforts with the objective of developing targets for future regional diamond drilling programs.

 

19


 

 

 

[Upper Beaver – Composite Longitudinal Section]

 

Regional Potential

 

As a part of an Ontario regional exploration budget for 2024 totalling $13.5 million for 19,400 metres of drilling, a planned surface exploration campaign has included drill holes to test the deep extensions of the Main Break east of the underground infrastructure of the SMC at Macassa and below historical mining levels of the Kirkland Lake camp to provide support for future underground exploration drifts.

 

Opportunities for future synergies in the Kirkland Lake camp include multiple known deposits owned by the Company. The nearest deposit to Upper Beaver is the Upper Canada past-producing gold mine, which lies 6 kilometres west-southwest. As at December 31, 2023, Upper Canada was estimated to contain 10.4 million tonnes of indicated mineral resources grading 2.15 g/t gold for 722,000 ounces of gold and 18.6 million tonnes of inferred mineral resources grading 3.11 g/t gold for 1.9 million ounces of gold, in open pit and underground mineral resources.

 

The Anoki-McBean deposits lie 6.5 kilometres southwest of Upper Beaver and host indicated mineral resources of 3.9 million tonnes grading 2.77 g/t gold for 349,000 ounces of gold and inferred mineral resources of 867,000 tonnes grading 3.84 g/t gold for 107,000 ounces of gold as at December 31, 2023.

 

Several other historical mineralized occurrences in the Kirkland Lake camp warrant additional exploration with the objective of potentially providing future mill feed at either Macassa and/or the Upper Beaver project, while benefiting from synergies with existing or future mining operations.

 

20


 

 

[Kirkland Lake Regional – Property and Geology Map]

 

Odyssey Project

 

In the second quarter of 2024, ramp development continued to exceed targets, reaching the third production level of East Gouldie (a depth of 832 metres) as at June 30, 2024. Equipment remotely tele-operated from surface (scoops, trucks, jumbos and cable bolters) has helped maintain the development performance, offsetting the increase in depth. The Company continued to develop the main ventilation system, with the completion of the future exhaust raise between levels 26 and 36 and the development of the fresh air ramp between Odyssey South and East Gouldie.

 

In the second quarter of 2024, shaft sinking activities advanced at an average rate of 2.5 metres per day, slightly ahead of target, and as at June 30, 2024, the shaft reached a depth of 680 metres. The pre-sinking of the shaft between levels 54 and 66 was completed in the second quarter and the remainder of the shaft will be excavated by conventional sinking methods. The excavation of station 54 was completed in the quarter and the excavation of the temporary loading pocket between levels 60 and 64 is ongoing, with construction expected to be initiated in September 2024 and commissioning expected in mid-2025.

 

Surface construction progressed as planned and on budget in the second quarter of 2024. Areas of focus included the main hoist building, phase 2 of the paste plant (to expand capacity to 20,000 tpd) and the operational complex. At the main hoist building, installation of the mechanical components of the service hoist was completed in the second quarter of 2024 and the installation of the electrical components and controls is ongoing. The conceptual engineering for the paste plant expansion was completed in the second quarter of 2024 and detailed engineering has started. The contractor for the construction of the main office and service building was selected and is expected to be on site in the third quarter of 2024 with construction expected to be completed by the end of 2025.

 

Exploration drilling at Odyssey totalled 24,182 metres during the second quarter (50,442 metres during the first half of 2024) with seven underground drill rigs and six surface drill rigs in operation, primarily targeting the East Gouldie and Odyssey deposits.

 

21


 

Drilling into the lower eastern extension of the East Gouldie mineralized envelope produced highlights that included: hole MEX24-311 returning 4.5 g/t gold over 6.5 metres at 1,571 metres depth, 770 metres east of the East Gouldie mineral reserves; hole MEX24-311Z returning 8.7 g/t gold over 3.8 metres at 1,687 metres depth, approximately 110 metres below hole MEX24-311; and hole MEX23-310ZA returning 2.3 g/t gold over 15.3 metres at 1,694 metres depth, 410 metres east of the mineral reserves.

 

The drilling remains on track to achieve a 150-metre drill spacing in an area that spans over 900 metres in strike length and 700 metres in elevation in the eastern extension of East Gouldie, with the objective of adding new inferred mineral resources for year-end 2024.

 

Drilling into a previously untested gap in the western extension of the East Gouldie deposit also intersected significant results, with hole MEX24-312 returning 2.5 g/t gold over 30.0 metres at 1,473 metres depth, 85 metres west of the East Gouldie mineral reserves; and hole MEX24-312Z returning 2.2 g/t gold over 10.5 metres at 1,414 metres depth, 260 metres west of the mineral reserves. These results are anticipated to have a positive impact on the mineral resource estimate at year-end 2024.

 

At a shallower depth, hole MEX24-314 intersected 2.8 g/t gold over 11.4 metres at 335 metres depth, including 9.8 g/t gold over 2.0 metres at 329 metres depth, in a potential extension of the East Malartic deposit. Follow-up drilling is planned in this new area of interest before the end of the year.

 

Selected recent drill intercepts from the East Gouldie and East Malartic deposits at the Odyssey mine are set out in the table and composite longitudinal section below.

 

Drill hole   Deposit   From
(metres)
    To
(metres)
    Depth of
midpoint
below
surface
(metres)
    Estimated
true width
(metres)
    Gold grade
(g/t)
(uncapped)
    Gold grade
(g/t)
(capped)*
 
MEX23-310ZA   East Gouldie     1,928.1       1,945.4       1,694       15.3       2.3       2.3  
MEX24-311   East Gouldie     1,890.5       1,897.5       1,571       6.5       4.5       4.5  
MEX24-311Z   East Gouldie     1,971.3       1,975.7       1,687       3.8       8.7       8.7  
MEX24-312   East Gouldie     1,634.0       1,666.4       1,473       30.0       2.5       2.5  
MEX24-312Z   East Gouldie     1,626.8       1,638.0       1,414       10.5       2.2       2.2  
MEX24-314   East Malartic     421.0       441.0       335       11.4       2.8       2.8  
including         421.0       424.5       329       2.0       9.8       9.8  

 

*Results from East Gouldie and East Malartic use capping factors of 20 g/t gold and 40 g/t gold, respectively.

 

22


 

 

[Odyssey mine – Composite Longitudinal Section]

 

Based on the positive results from the exploration program near the Odyssey mine during the first half of 2024, the Company has approved a supplemental exploration budget of $12.0 million for 68,000 metres of near-mine drilling during the second half of the year. The objective is to further expand the East Gouldie deposit footprint laterally and add inferred mineral resources in support of a potential future Shaft #2 and the broader "Fill the Mill" strategy at the Canadian Malartic complex.

 

In addition, the regional exploration program at Canadian Malartic is receiving a supplemental exploration budget of $4.5 million for 16,500 metres of additional drilling during the second half of 2024, to further investigate the eastern portion of the Canadian Malartic property package in support of the Fill the Mill strategy.

 

These supplemental budgets are in addition to the Company's previously disclosed exploration budget for 2024 at Canadian Malartic of approximately $20.4 million for 137,000 metres of drilling at Odyssey and at regional targets.

 

Detour Lake

 

On June 19, 2024, the Company released the results of a technical study reflecting the potential for a concurrent underground operation to accelerate access to higher grade ore and to increase annual production to approximately one million ounces for 14 years starting in 2030 (see the Company's news release dated June 19, 2024).

 

The technical study assumed an underground mining rate of approximately 11,200 tpd (equivalent to 4.0 million tonnes per annum ("Mtpa")) starting in 2030, combined with a mill expansion to 79,450 tpd (equivalent to 29 Mtpa) starting in 2028. Annual production is expected to increase by approximately 43% or 300,000 ounces of gold per year, from 2030 to 2043 to approximately one million ounces per year when compared to average annual production in years 2024 to 2029. The underground project and mill throughput optimization to 29 Mtpa are expected to generate an after-tax IRR of approximately 18% using a gold price assumption of $1,900 per ounce and a C$/US$ foreign exchange rate of 1.34. At a gold price assumption of $2,300 per ounce and a C$/US$ foreign exchange rate of 1.34, the underground project and mill throughput optimization to 29 Mtpa are expected to generate an after-tax IRR of approximately 25%.

 

23


 

Based on strong risk-adjusted returns for the Detour Lake underground project, the Company has approved a $100.0 million investment over approximately three years to develop a 2.0-kilometre exploration ramp to a depth of 270 metres in order to collect a bulk sample and to facilitate infill and expansion drilling of the current underground mineral resource. Approximately $19.6 million is forecast to be spent in the second half of 2024 related to the construction of surface facilities and site preparation.

 

Exploration drilling at Detour Lake during the second quarter of 2024 totalled 72,000 metres (130,000 metres during the first half of 2024), including infill drilling into the newly defined high-grade corridor at underground depths in the West Pit zone and infill drilling into the West Pit Extension zone at underground depths immediately west of the West Pit mineral resources and next to the proposed exploration ramp for the underground project.

 

In the high-grade corridor in the West Pit zone, highlights included: hole DLM24-843 returning 4.0 g/t gold over 22.3 metres at 413 metres depth, including 18.7 g/t gold over 2.1 metres at 414 metres depth; hole DLM24-874 returning 2.5 g/t gold over 10.3 metres at 291 metres depth and 4.4 g/t gold over 30.1 metres at 550 metres depth, including 17.6 g/t gold over 3.9 metres at 557 metres depth; and hole DLM24-897E returning 26.9 g/t gold over 2.8 metres at 235 metres depth and 3.3 g/t gold over 11.1 metres at 261 metres depth.

 

To the west in the West Pit zone near the proposed exploration ramp, highlights included: hole DLM24-873 returning 37.3 g/t gold over 3.5 metres at 282 metres depth; and hole DLM24-930A returning 20.6 g/t gold over 5.5 metres at 280 metres depth and 1.8 g/t gold over 60.5 metres at 348 metres depth.

 

From infill drilling into the West Pit Extension zone, highlights included: hole DLM24-884 returning 4.3 g/t gold over 22.5 metres at 429 metres depth, including 24.5 g/t gold over 3.5 metres at 432 metres depth, and 3.7 g/t gold over 13.4 metres at 551 metres depth; hole DLM24-895AW returning 28.8 g/t gold over 3.6 metres at 570 metres depth; and hole DLM24-873 returning 37.3 g/t gold over 3.5 metres at 282 metres depth.

 

24


 

Selected recent drill intercepts from the West Pit Underground and West Pit Extension zones at Detour Lake are set out in the table and composite longitudinal section below.

 

Drill hole   Zone   From
(metres)
    To
(metres)
    Depth of
midpoint
below
surface
(metres)
    Estimated
true width
(metres)
    Gold grade
(g/t)
(uncapped)*
 
DLM24-839   West Pit Extension     353.0       362.0       321       7.2       5.2  
and   West Pit Extension     395.0       419.4       365       19.6       3.9  
including         398.0       402.0       358       3.2       12.6  
DLM24-843   West Pit Underground     505.8       530.3       413       22.3       4.0  
including         519.2       521.5       414       2.1       18.7  
DLM24-851   West Pit Extension     350.0       392.3       318       36.1       2.6  
including         375.3       378.7       323       2.9       23.5  
DLM24-855   West Pit Extension     481.9       509.0       433       22.8       2.4  
including         486.0       495.0       429       7.6       5.1  
DLM24-860   West Pit Extension     583.9       619.0       524       30.2       2.2  
including         583.9       598.0       515       12.1       4.4  
DLM24-870   West Pit Underground     207.6       228.0       182       17.7       3.3  
including         221.1       225.0       186       3.4       11.0  
DLM24-871   West Pit Underground     378.5       396.0       313       15.6       4.7  
including         378.5       383.6       309       4.5       13.6  
DLM24-873   West Pit Underground     346.1       350.0       282       3.5       37.3  
DLM24-874   West Pit Underground     385.0       396.0       291       10.3       2.5  
and         764.0       795.0       550       30.1       4.4  
including         789.0       793.0       557       3.9       17.6  
DLM24-884   West Pit Underground     526.3       551.0       429       22.5       4.3  
including         540.6       544.4       432       3.5       24.5  
and   West Pit Underground     696.0       710.5       551       13.4       3.7  
DLM24-891C   West Pit Underground     635.0       662.0       562       23.4       1.7  
including         650.8       662.0       569       9.7       3.4  
DLM24-895AW   West Pit Extension     676.0       680.0       570       3.6       28.8  
DLM24-897E   West Pit Underground     305.0       308.0       235       2.8       26.9  
and   West Pit Underground     336.0       348.0       261       11.1       3.3  
DLM24-899A   West Pit Extension     578.0       595.9       495       15.8       4.4  
DLM24-903   West Pit Extension     403.0       418.0       344       13.2       3.6  
and         438.0       446.8       369       7.8       12.8  
DLM24-908E   West Pit Underground     727.0       775.0       576       45.6       2.1  
including         764.0       774.0       589       9.5       6.5  
and   West Pit Underground     791.0       819.0       613       26.7       2.1  
including         800.0       808.0       612       7.6       5.5  
DLM24-911A   West Pit Extension     722.3       750.2       636       24.6       2.4  
including         730.9       734.0       633       2.7       13.9  
and   West Pit Extension     761.0       792.0       668       27.4       2.4  
including         779.8       782.9       672       2.7       16.8  
and   West Pit Extension     827.6       835.0       711       6.6       9.5  
DLM24-916W   West Pit Extension     460.7       498.1       408       32.2       3.2  
including         486.8       491.7       416       4.2       12.8  
DLM24-923   West Pit Extension     603.4       630.0       520       23.2       3.3  
including         603.4       606.5       520       2.7       17.4  
DLM24-927   West Pit Extension     445.8       450.7       375       4.3       15.7  
DLM24-930A   West Pit Underground     349.0       355.0       280       5.5       20.6  
and   West Pit Underground     411.0       476.4       348       60.5       1.8  

 

*Results from Detour Lake are uncapped.

 

25


 

 

[Detour Lake – Composite Longitudinal Section]

 

Further details on the mine-site and regional exploration programs at Detour Lake in 2024 are set out in the Detour Lake-focused news release dated June 19, 2024.

 

With the success of the exploration program at Detour Lake during the first half of the year, the Company has approved a supplemental exploration budget of $10.9 million for 55,000 metres of drilling during the second half of 2024 to infill and expand the underground high-grade corridor to accelerate the de-risking of the underground project. This is in addition to the previously disclosed exploration budget for 2024 at Detour Lake of $27.7 million for 160,000 metres of drilling.

 

Hope Bay – Step-Out Drilling Continues to Extend Madrid's High-Grade Patch 7 Zone at Depth and Laterally

 

Exploration drilling at Hope Bay during the second quarter of 2024 totalled 35,400 metres (66,100 metres during the first half of 2024) and continued to return strong results at the Madrid deposit within the Patch 7 zone and in the gap area between the Patch 7 and Suluk zones.

 

Infill drilling into the high-grade shoot immediately north of the Patch 7 mineral resource was highlighted by hole HBM24-206A returning 26.7 g/t gold over 2.8 metres at 405 metres depth, including 75.0 g/t gold over 0.9 metres at 404 metres depth, and 17.0 g/t gold over 25.8 metres at 419 metres depth, including 35.6 g/t gold over 6.5 metres at 412 metres depth; hole HBM24-207 returning 7.2 g/t gold over 8.1 metres at 559 metres depth, including 8.7 g/t gold over 4.5 metres at 558 metres depth; and hole HBM24-209 returning 30.8 g/t gold over 2.4 metres at 559 metres depth.

 

The high-grade shoot remains open both up-plunge and down-plunge with significant potential for mineral resource expansion.

 

This emerging new mineralized area continues to show excellent continuity as well as grades and thicknesses greater than average for the Madrid deposit. It is anticipated that the drilling program in this area in 2024 will have positive impacts on the mineral resource estimate at year-end 2024 and on mining scenarios for potential project redevelopment.

 

At shallower depths in the same area of Patch 7, hole HBM24-191 returned 9.7 g/t gold over 6.3 metres at 242 metres depth and hole HBM24-201 returned 5.3 g/t gold over 18.0 metres at 278 metres depth. Drilling in this shallower area is confirming the presence of the same structures and favourable host rocks encountered in the main Patch 7 mineral resources located several hundred metres to the south.

 

Exploration during the second quarter also included widely spaced, expansion drilling at greater depth approximately 600 metres to the north in the largely untested gap area between the Patch 7 and Suluk zones, highlighted by hole HBM24-177B returning 9.5 g/t gold over 8.6 metres at 750 metres depth, including 15.5 g/t gold over 3.7 metres at 753 metres depth; and hole HBM24-183 returning 14.1 g/t gold over 5.0 metres at 577 metres depth, including 25.1 g/t gold over 2.3 metres at 575 metres depth.

 

26


 

Selected recent drill intercepts from the Patch 7 zone at the Madrid deposit are set out in the table and composite longitudinal section below.

 

Drill hole   From
(metres)
    To
(metres)
    Depth of
midpoint below
surface
(metres)
    Estimated
true width
(metres)
    Gold grade
(g/t)
(uncapped)
    Gold grade
(g/t)
(capped)*
 
HBM24-177B     864.5       883.8       750       8.6       9.5       9.5  
including     873.9       882.0       753       3.7       15.5       15.5  
HBM24-183     684.4       693.5       577       5.0       19.0       14.1  
including     684.4       688.6       575       2.3       35.8       25.1  
HBM24-188     609.4       633.6       475       15.2       5.6       5.6  
including     611.0       620.0       471       5.7       4.6       4.6  
including     626.0       633.6       481       4.8       10.9       10.9  
HBM24-189     552.3       581.8       443       12.7       6.0       6.0  
including     552.3       575.2       441       9.9       6.9       6.9  
HBM24-191     289.1       297.0       242       6.3       9.7       9.7  
HBM24-201     357.0       375.0       278       18.0       10.8       5.3  
HBM24-206A     529.0       532.0       405       2.8       28.0       26.7  
including     529.0       530.0       404       0.9       79.0       75.0  
and     539.1       566.0       419       25.8       20.8       17.0  
including     539.1       546.0       412       6.5       50.7       35.6  
HBM24-207     634.8       651.0       559       8.1       7.2       7.2  
including     637.1       646.1       558       4.5       8.7       8.7  
HBM24-209     643.0       646.0       559       2.4       53.7       30.8  

 

*Results from the Madrid deposit at Hope Bay use a capping factor ranging from 50 g/t to 75 g/t gold depending on the mineralized domain.

 

 

[Madrid Deposit at Hope Bay – Composite Longitudinal Section]

 

Given the positive drill results at Madrid during the first half of 2024, the Company has approved a supplemental exploration budget at Hope Bay for the second half of 2024 of $22.6 million for an additional 62,000 metres of drilling to infill and expand Patch 7 to accelerate mineral reserve addition in advance of a potential project decision in 2025-26. This is in addition to the previously disclosed budget for 2024 at the Hope Bay project of $22.0 million for 50,000 metres of drilling.

 

27


 

In early July, the Company finalized an asset purchase agreement with North Arrow Minerals Inc. to acquire a 100% interest in the Oro gold property in the northeastern extension of the Hope Bay gold belt for a cash consideration of C$1.75 million. The Oro property comprises 4,103 hectares consisting of five leases with multiple, historical near-surface gold mineralization occurrences.

 

San Nicolás Copper Project

 

In the second quarter of 2024, Minas de San Nicolás continued engagement with government and stakeholders in support of the permit review and continued to advance feasibility study work, with plans to initiate detailed engineering in the first half of 2025. The Minas de San Nicolás team submitted the change of land use permit application ("ETJ") on June 14, 2024 and a Supplementary Information Package in response to the regulator's enquiries on their MIA-R permit application ("EIA") on July 5, 2024. Project approval is expected to follow, subject to receipt of permits and the results of the feasibility study.

 

ABITIBI REGION, QUEBEC

 

LaRonde – Strong Operational Performance Driven by Higher Grades; Automation Initiatives at LaRonde Zone 5 Continue to Exceed Targets

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
LaRonde – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     680       660       1,360       1,368  
Tonnes of ore milled per day     7,473       7,253       7,473       7,558  
Gold grade (g/t)     4.05       3.82       3.73       3.77  
Gold production (ounces)     82,334       76,780       150,698       156,387  
Production costs per tonne (C$)   $ 128     $ 174     $ 158     $ 145  
Minesite costs per tonne (C$)15   $ 157     $ 151     $ 157     $ 154  
Production costs per ounce   $ 775     $ 1,117     $ 1,051     $ 944  
Total cash costs per ounce   $ 816     $ 884     $ 929     $ 922  

 

Gold Production

 

Second Quarter of 2024 – Gold production increased when compared to the prior-year period primarily due to a higher volume of ore mined and milled driven by strong operational performance and higher gold grades as expected under the mining sequence, partially offset by lower recovery

 

First Six Months of 2024 – Gold production decreased when compared to the prior-year period due to lower gold grades and a lower volume of ore milled

 

Production Costs

 

Second Quarter of 2024 – Production costs per tonne decreased when compared to the prior-year period primarily due to the higher volume of ore milled in the current period, partially offset by the timing of inventory sales and higher milling and royalty costs at the LaRonde mine. Production costs per ounce decreased when compared to the prior-year period primarily due to higher gold grades and lower production costs per tonne

 

First Six Months of 2024 – Production costs per tonne increased when compared to the prior-year period primarily due to stockpile consumption, the timing of inventory sales, higher milling and royalty costs at the LaRonde mine and lower volumes of ore milled. Production costs per ounce increased when compared to the prior-year period primarily due to higher production costs per tonne and lower gold grades

 

 

15 Minesite costs per tonne is a non-GAAP measure that is not standardized under IFRS and is reported on a per tonne of ore milled basis. For a description of the composition and usefulness of this non-GAAP measure and a reconciliation to production costs see "Note Regarding Certain Measures of Performance" below.

 

28


 

Minesite and Total Cash Costs

 

Second Quarter of 2024 – Minesite costs per tonne increased when compared to the prior-year period primarily due to higher milling and royalty costs at the LaRonde mine, partially offset by higher volume of ore milled. Total cash costs per ounce decreased when compared to the prior-year period primarily due to higher gold grades, partially offset by higher minesite costs per tonne

 

First Six Months of 2024 – Minesite costs per tonne increased when compared to the prior-year period primarily due to stockpile consumption and higher milling and royalty costs and lower volume of ore milled. Total cash costs per ounce increased when compared to the prior-year period primarily due to lower gold grades and higher minesite costs per tonne

 

Highlights

 

Gold production in the quarter was higher than forecast as a result of higher grades and higher volume milled

 

The Company continued its automation initiatives at the LaRonde zone 5 mine ("LZ5") and exceeded its automation target by 22%. Approximately 1,800 tpd were moved during the quarter through automated scoops and trucks, which contributed to the strong overall performance of the site at an average 3,450 tpd

 

The LZ5 processing facility was placed on care and maintenance during the third quarter of 2023 and is on track to restart in the third quarter of 2024. During the downtime, the Company continues to overhaul the facility's leach tanks and is refurbishing the ore silo. Ore from LZ5 will continue to be processed at the LaRonde mill until the restart of the LZ5 processing facility

 

A shutdown was scheduled for the third quarter of 2024 for 14 days at the LaRonde mine and 11 days at the LaRonde mill and was completed in July

 

On June 24, 2024, a seismic event of magnitude 4.1 on the Richter scale, occurred at the LaRonde mine. Safety protocols were followed, the mine was evacuated and no workers were injured. The dynamic ground support performed as designed. While the mine was shutdown for approximately two days, the mill continued to operate at normal levels using surface stockpiles. Site-specific expertise in mitigating seismic risk has been developed by the Company over many years of operations at LaRonde. The Company's objective remains to address the seismic risk by continuously improving mitigation measures to keep a safe work environment while maintaining reasonable production rates. These mitigation measures include non-entry protocols, dynamic ground support and, increasingly, remote operation from surface

 

At the LaRonde mill, the focus remained on improving mill recoveries by optimizing the blending of ore from the LaRonde mine, 11-3 zone, LZ5, Goldex and Akasaba West

 

During the quarter, LaRonde was recognized for environmental and social performance, receiving the following awards:

 

TSM Excellence Award from the Mining Association of Canada for the transition to filtered tailings management – this award acknowledges innovative projects and initiatives that support sustainable development

 

Community relations award from the Quebec Mining Association ("QMA") – recognition of the collaboration agreement with the Abitibiwinni First Nations and the Nikan Project, which facilitates integration and retention of Indigenous workers

 

29


 

Canadian Malartic – Higher Tonnes Milled Drive Strong Production; Record Development Metres and Production from Odyssey South

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Canadian Malartic – Operating Statistics*   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     5,182       4,882       10,355       9,406  
Tonnes of ore milled per day     56,945       53,648       56,896       51,967  
Gold grade (g/t)     1.17       1.22       1.19       1.21  
Gold production* (ounces)     180,871       177,755       367,777       258,440  
Production costs per tonne (C$)   $ 38     $ 40     $ 35     $ 38  
Minesite costs per tonne (C$)   $ 42     $ 39     $ 42     $ 39  
Production costs per ounce   $ 798     $ 811     $ 737     $ 780  
Total cash costs per ounce   $ 871     $ 772     $ 860     $ 779  

 

* Gold production reflects Agnico Eagle's 50% interest in Canadian Malartic up to and including March 30, 2023 and 100% interest thereafter. Tonnage of ore milled is reported on a 100% basis for both periods.

 

Gold Production

 

Second Quarter of 2024 – Gold production increased when compared to the prior-year period primarily due to higher throughput resulting from strong operational performance at the Barnat pit and Odyssey mine, partially offset by lower gold grades from increased ore sourced from the low-grade stockpile

 

First Six Months of 2024 – Gold production increased when compared to the prior-year period due to the increase in the Company's ownership percentage between periods from 50% to 100% as a result of the closing of the acquisition of the Yamana Transaction and higher throughput, partially offset by lower gold grades resulting from increased ore sourced from the low-grade stockpile

 

Production Costs

 

Second Quarter of 2024 – Production costs per tonne decreased when compared to the prior-year period primarily due to a higher volume of ore milled and the timing of inventory adjustments during the comparative period. Production costs per ounce decreased when compared to the prior-year period due to more ounces of gold produced in the current period

 

First Six Months of 2024 – Production costs per tonne decreased when compared to the prior-year period primarily due to a higher volume of ore milled and the timing of inventory adjustments during the comparative period. Production costs per ounce decreased when compared to the prior-year period due to lower production costs per tonne, partially offset by lower gold grades in the current period

 

Minesite and Total Cash Costs

 

Second Quarter of 2024 – Minesite costs per tonne increased when compared to the prior-year period due to the milling of low-grade stockpiles and higher royalty costs during the quarter, partially offset by higher volume of ore milled. Total cash costs per ounce increased when compared to the prior-year period primarily due to the same factors that resulted in higher minesite costs per tonne and lower gold grades in the current period

 

First Six Months of 2024 – Minesite costs per tonne increased when compared to the prior-year period due to the consumption of low-grade stockpiles and higher royalty costs, partially offset by higher volume of ore milled. Total cash costs per ounce increased when compared to the prior-year period primarily due to the same factors that resulted in higher minesite costs per tonne and lower gold grades in the current period

 

30


 

Highlights

 

Higher mill throughput, higher gold grades from the Barnat pit due to mine sequencing and higher mill recoveries than planned, along with the record production from Odyssey, resulted in better than planned quarterly gold production at Canadian Malartic

 

At Odyssey South, total metres developed during the quarter were a record at 3,870 metres. Gold production and mining rate were above plan at approximately 22,300 ounces of gold and 3,750 tpd, respectively. The strong operational performance was supported by higher than planned equipment availability and the addition of 65 tonne haulage trucks

 

Stope reconciliation at Odyssey South remains positive, primarily from the contribution of the internal zones, which resulted in approximately 13% more ounces of gold produced than anticipated during the second quarter

 

At the Canadian Malartic pit, the Company continued the construction of the central berm (approximately 95% complete at June 30, 2024) in preparation for in-pit tailings disposal, which began in July 2024

 

An extended shutdown at the Canadian Malartic mill is planned for the third quarter of 2024 totalling 10 days (approximately an additional 5 days from the original plan) due to the acceleration of maintenance work on the tailings thickener drive assembly

 

An update on the Odyssey mine development, construction and exploration highlights is set out in the Update on Key Value Drivers and Pipeline Projects section above

 

During the quarter, Canadian Malartic was recognized for its health and safety performance and received the following awards:

 

John T. Ryan Eastern Canada Regional Safety award from the Canadian Institute of Mining, Metallurgy and Petroleum – awarded to an open pit mine which experienced the lowest reportable injury frequency in the previous year

 

F.J. O'Connell surface operations award from the QMA – recognizing workplace health and safety performance of QMA members

 

Goldex – Record Tonnage Milled Since Re-Start in 2013; Production from Deep 2 Zone Commenced

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Goldex Complex – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     765       761       1,525       1,459  
Tonnes of ore milled per day     8,407       8,363       8,379       8,061  
Gold grade (g/t)     1.62       1.74       1.63       1.74  
Gold production (ounces)     33,750       37,716       68,138       71,739  
Production costs per tonne (C$)   $ 59     $ 50     $ 59     $ 52  
Minesite costs per tonne (C$)   $ 60     $ 51     $ 60     $ 51  
Production costs per ounce   $ 980     $ 747     $ 973     $ 781  
Total cash costs per ounce   $ 864     $ 776     $ 906     $ 792  

 

Gold Production

 

Second Quarter of 2024 – Gold production decreased when compared to the prior-year period primarily due to lower average gold grades resulting from increased ore sourced from Akasaba West

 

First Six Months of 2024 – Gold production decreased when compared to the prior-year period primarily due to lower average gold grades resulting from increased ore sourced from Akasaba West, partially offset by a higher volume of ore processed

 

31


 

Production Costs

 

Second Quarter and First Six Months of 2024 – Production costs per tonne increased when compared to the prior-year periods primarily due to higher underground production costs, higher open pit mining costs, higher milling costs and a lower deferred stripping adjustment associated with the Akasaba West project, partially offset by higher volume of ore milled. Production costs per ounce increased when compared to the prior-year periods due to the same factors that resulted in higher production costs per tonne and lower gold grades

 

Minesite and Total Cash Costs

 

Second Quarter and First Six Months of 2024 – Minesite costs per tonne increased when compared to the prior-year periods due to the same reasons outlined above for the higher production costs per tonne. Total cash costs per ounce increased when compared to the prior-year periods due to the same reasons outlined above for the higher production costs per ounce

 

Highlights

 

Solid gold production during the quarter was driven by record mill throughput since the re-start of Goldex operations in 2013, including record throughput in May of approximately 289,000 tonnes milled

 

Development of the Deep 2 zone continued to advance as planned during the quarter and began initial production in June 2024

 

During the quarter, Goldex was recognized for its health and safety performance and received the following awards:

 

John T. Ryan National award from the Canadian Institute of Mining, Metallurgy and Petroleum – awarded to a metal mine which experienced the lowest reportable injury frequency in the previous year

 

F.J. O'Connell award for underground operations from the QMA – recognizing the workplace health and safety performance of QMA members

 

ABITIBI REGION, ONTARIO

 

Detour Lake – Mill Throughput Improved Quarter-over-Quarter; Pathway to One Million Ounces Provided in June

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Detour Lake – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     6,792       6,800       13,294       13,197  
Tonnes of ore milled per day     74,637       74,725       73,044       72,912  
Gold grade (g/t)     0.86       0.85       0.84       0.85  
Gold production (ounces)     168,247       169,352       318,998       331,209  
Production costs per tonne (C$)   $ 24     $ 22     $ 26     $ 23  
Minesite costs per tonne (C$)   $ 26     $ 26     $ 27     $ 26  
Production costs per ounce   $ 715     $ 666     $ 791     $ 685  
Total cash costs per ounce   $ 791     $ 731     $ 829     $ 750  

 

Gold Production

 

Second Quarter of 2024 – Gold production decreased slightly when compared to the prior-year period primarily due to lower metallurgical recovery as a result of lower grinding efficiency related to the change in grinding media during the quarter, partially offset by higher gold grades

 

32


 

First Six Months of 2024 – Gold production decreased when compared to the prior-year period primarily due to lower metallurgical recovery, mainly due to abnormal chipping of grinding media affecting grinding efficiency and lower gold grades, partially offset by higher throughput

 

Production Costs

 

Second Quarter of 2024 – Production costs per tonne increased when compared to the prior-year period primarily due to higher milling costs as a result of the change in grinding media in the SAG mill and higher mining costs, partially offset by stockpile build-up in the current period. Production costs per ounce increased when compared to the prior-year period due to the higher production costs per tonne, partially offset by the higher gold grades

 

First Six Months of 2024 – Production costs per tonne increased when compared to the prior-year period primarily due to higher milling costs as a result of the change in grinding media in the SAG mill and higher mining costs, partially offset by stockpile build-up in the current period and by higher volume of ore milled in the current period. Production costs per ounce increased when compared to the prior-year period due to the same factors resulting in higher production costs per tonne and lower gold grades

 

Minesite and Total Cash Costs

 

Second Quarter of 2024 – Minesite costs per tonne remained unchanged when compared to the prior-year period. Total cash costs per ounce increased when compared to the prior-year period due to lower metallurgical recovery, partially offset by higher gold grades

 

First Six Months of 2024 – Minesite costs per tonne increased when compared to the prior-year period due to the same reasons outlined above that resulted in higher production costs per tonne. Total cash costs per ounce increased when compared to the prior-year period due to the same reasons outlined above that resulted in higher production costs per ounce

 

Highlights

 

The mill throughput rate of 74,637 tpd in the second quarter of 2024 increased when compared to the first quarter primarily due to the replacement of the defective grinding media in the SAG mill and record quarterly mill availability of 93.0%. The installation of new instrumentation in the SAG mill to optimize the load balance between the SAG mills and ball mills contributed to achieving monthly throughput performance in June 2024 of 81,324 tpd. Other initiatives that are expected to help reach the targeted rate of 76,700 tpd by the end of 2024 include the installation of a new ball mill discharge grizzly, a SAG discharge box upgrade in one of the lines and installation of variable speed drive to the secondary crushers

 

Phase 2 of the open pit was completed in the second quarter of 2024. Assembly of the new Komatsu rope shovel was approximately 80% complete as at June 30, 2024, with commissioning expected in the third quarter of 2024. The new rope shovel is expected to add increased capacity required per the life of mine plan and will replace a diesel shovel of lower capacity

 

Metallurgical recovery remained below plan in the second quarter of 2024 as a result of lower grinding efficiency related to the change in grinding media. The Company continues to work with its suppliers to optimize the grinding efficiency in the SAG mill and has scheduled further tests of new grinding media in the third quarter of 2024

 

The expansion of the mine maintenance shop to support increased mining rates and a larger production fleet is ongoing. The new mining service facility is expected to be completed in 2025

 

An upgrade of the 230kV main substation is planned to improve the power quality at the mine and improve the site readiness for potential projects such as the Detour Lake underground and mill expansion. The engineering was completed and all long lead items were ordered in the second quarter of 2024. The upgrades related to power quality are expected to be completed in 2024 and those related to improving site readiness for future projects are expected in 2025

 

33


 

An update on the underground project study and exploration results is set out in the Update on Key Value Drivers and Pipeline Projects section above

 

Macassa – Consecutive Quarters of Record Mill Throughput; Continued Productivity Improvements from Workforce Ramp-Up and Equipment Availability

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Macassa – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     152       112       286       199  
Tonnes of ore milled per day     1,670       1,231       1,571       1,099  
Gold grade (g/t)     13.44       16.16       14.77       19.29  
Gold production (ounces)     64,062       57,044       132,321       121,159  
Production costs per tonne (C$)   $ 459     $ 464     $ 470     $ 519  
Minesite costs per tonne (C$)   $ 476     $ 503     $ 484     $ 539  
Production costs per ounce   $ 797     $ 676     $ 746     $ 631  
Total cash costs per ounce   $ 833     $ 747     $ 770     $ 672  

 

Gold Production

 

Second Quarter and First Six Months of 2024 – Gold production increased when compared to the prior-year periods primarily due to higher throughput as a result of productivity gains resulting from new ventilation infrastructure, improved equipment availability and the addition of ore sourced from the Near Surface deposit, partially offset by lower gold grades related to the addition of ore sourced from the Near Surface deposit

 

Production Costs

 

Second Quarter and First Six Months of 2024 – Production costs per tonne decreased when compared to the prior-year periods due to the higher volume of ore milled in the current periods, partially offset by higher underground development and mining costs. Production costs per ounce increased when compared to the prior-year periods due to lower gold grades and higher underground development and mining costs

 

Minesite and Total Cash Costs

 

Second Quarter and First Six Months of 2024 – Minesite costs per tonne decreased when compared to the prior-year periods due to the same reasons outlined above that resulted in lower production costs per tonne. Total cash costs per ounce increased when compared to the prior-year periods due to the same reasons outlined above that resulted in the higher production costs per ounce

 

Highlights

 

Macassa recorded its best quarterly safety performance since the merger between Agnico Eagle and Kirkland Lake Gold. The Macassa mine rescue team won first place in the Kirkland Lake District Competition and in the Ontario Provincial Mine Rescue Competition

 

During the second quarter of 2024, Macassa continued to demonstrate sustained productivity gains with record quarterly volume skipped and record quarterly mill throughput. Gold grades were lower than plan primarily due to processing more ore from the lower grade Near Surface deposit

 

At the Portal (ramp access to the Near Surface and AK deposits), production from long hole stopes in the Near Surface deposit continued in the second quarter of 2024, with volume of ore mined and milled exceeding planned targets

 

Construction of the new paste plant was 50% complete as at June 30, 2024, and is on schedule for commissioning in the first half of 2025

 

34


 

NUNAVUT

 

Meliadine – Solid Quarterly Performance Despite Earlier than Planned Caribou Migration; Phase 2 Mill Expansion Complete

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Meliadine – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     421       461       917       937  
Tonnes of ore milled per day     4,626       5,066       5,038       5,177  
Gold grade (g/t)     6.79       6.14       6.49       6.13  
Gold production (ounces)     88,675       87,682       184,400       178,149  
Production costs per tonne (C$)   $ 278     $ 230     $ 265     $ 229  
Minesite costs per tonne (C$)   $ 254     $ 261     $ 249     $ 250  
Production costs per ounce   $ 969     $ 899     $ 973     $ 898  
Total cash costs per ounce   $ 892     $ 1,019     $ 918     $ 978  

 

Gold Production

 

Second Quarter and First Six Months of 2024 – Gold production increased when compared to the prior-year periods primarily due to higher gold grades as expected under the planned the mining sequence, partially offset by lower throughput

 

Production Costs

 

Second Quarter and First Six Months of 2024 – Production costs per tonne increased when compared to the prior-year periods primarily due to the timing of inventory sales, higher underground services and royalty costs and a lower volume of ore milled in the current periods, partially offset by the buildup of stockpiles. Production costs per ounce increased when compared to the prior-year periods due to the same reasons that resulted in higher production costs per tonne, partially offset by higher gold grades in the current periods

 

Minesite and Total Cash Costs

 

Second Quarter and First Six Months of 2024 – Minesite costs per tonne decreased when compared to the prior-year period primarily due to the buildup in stockpiles, partially offset by the lower volume of ore milled. Total cash costs per ounce decreased when compared to the prior-year period primarily due to higher gold grades and the same reasons that resulted in lower minesite costs per tonne

 

Highlights

 

Gold production during the quarter was slightly affected by lower throughput as a result of an earlier than anticipated caribou migration period. Given the operational downtime due to the migration, the Company took the opportunity to rehabilitate the underground ramp during this period. The Company is adapting its Caribou Readiness Plan, which includes earlier deployment of sea can barriers, crushing of ore stockpiles, and stocking of surface and underground materials, to further mitigate the impact of early caribou migration in future years

 

The mill expansion project was completed during the second quarter and commissioning is expected in the third quarter of 2024. Throughput at the mill is expected to ramp up to 6,000 tpd by year-end 2024

 

During the first quarter of 2024, the Company submitted a proposal to the Nunavut Water Board to amend the current Type A Water license to include tailings, water and waste management infrastructure at the Pump, F-zone, Wesmeg and Discovery deposits. A technical meeting with the Nunavut Water Board and meetings with the community took place during the second quarter of 2024. Public hearings are expected to take place in the third quarter of 2024. The Company now expects permits to be received in the first quarter of 2025

 

35


 

During the quarter, Meliadine was recognized for its health and safety performance and received the John T. Ryan Regional award from the Canadian Institute of Mining, Metallurgy and Petroleum for the second consecutive year – awarded to a metal mine for the Prairie Provinces and Territories which experienced the lowest reportable injury frequency in the previous year

 

Meadowbank – Higher Grades and Record Ore Hauling at the Underground Operations Drive Production

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Meadowbank Complex – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     990       845       2,061       1,828  
Tonnes of ore milled per day     10,879       9,286       11,324       10,099  
Gold grade (g/t)     4.36       3.79       4.22       3.85  
Gold production (ounces)     126,419       94,775       254,193       205,885  
Production costs per tonne (C$)   $ 169     $ 186     $ 156     $ 181  
Minesite costs per tonne (C$)   $ 160     $ 178     $ 155     $ 176  
Production costs per ounce   $ 973     $ 1,240     $ 933     $ 1,202  
Total cash costs per ounce   $ 922     $ 1,156     $ 930     $ 1,144  

 

Gold Production

 

Second Quarter of 2024 – Gold production increased when compared to the prior-year period primarily due to higher throughput as operations in the prior period were affected by unplanned mill shutdowns from the caribou migration, and higher gold grades as expected under the mine plan

 

First Six Months of 2024 – Gold production increased when compared to the prior-year period primarily due to higher throughput as the comparative period was affected by unplanned downtime at the SAG mill and unplanned mill shutdowns from the caribou migration, and higher gold grades as expected under the mine plan

 

Production Costs

 

Second Quarter and First Six Months of 2024 – Production costs per tonne decreased when compared to the prior-year periods due to a higher volume of ore milled. Production costs per ounce decreased when compared to the prior-year periods primarily due to higher gold grades and lower production costs per tonne

 

Minesite and Total Cash Costs

 

Second Quarter and First Six Months of 2024 – Minesite costs per tonne decreased when compared to the prior-year periods due to the same reasons outlined above that resulted in the lower production costs per tonne. Total cash costs per ounce decreased when compared to the prior-year periods due to the same reasons outlined above that resulted in the lower production costs per ounce

 

Highlights

 

Gold production was higher than expected due to the operational performance at both the open pit and underground operations

 

Open pit operation continued to deliver strong haulage performance during the second quarter of 2024, achieving a monthly record in June 2024 benefiting from both increased equipment availability and shorter cycle times

 

The underground operation also had another strong quarter, setting quarterly performance records for hauling, production drilling and cemented rockfill in the second quarter of 2024. This was accomplished through continued productivity gains that demonstrated sustained improvement through the full mining cycle and increased adherence and compliance to plan

 

36


 

AUSTRALIA

 

Fosterville – Record Quarterly Ore Mined and Record Monthly Mill Throughput

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Fosterville – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     234       176       406       324  
Tonnes of ore milled per day     2,571       1,934       2,231       1,790  
Gold grade (g/t)     9.06       14.77       9.68       16.49  
Gold production (ounces)     65,963       81,813       122,532       168,371  
Production costs per tonne (A$)   $ 237     $ 308     $ 264     $ 335  
Minesite costs per tonne (A$)   $ 259     $ 304     $ 265     $ 321  
Production costs per ounce   $ 558     $ 438     $ 575     $ 430  
Total cash costs per ounce   $ 608     $ 436     $ 575     $ 416  

 

Gold Production

 

Second Quarter and First Six Months of 2024 – Gold production decreased when compared to the prior-year periods primarily due to the lower gold grades from mine sequencing, partially offset by higher throughput

 

Production Costs

 

Second Quarter of 2024 – Production costs per tonne decreased when compared to the prior-year period due to a higher volume of ore mined and milled, partially offset by higher mining costs associated with the extra volume, higher royalty costs and the build-up of stockpiles. Production costs per ounce increased when compared to the prior-year period due to lower gold production, partially offset by lower production costs per tonne and the weaker Australian dollar relative to the U.S. dollar

 

First Six Months of 2024 – Production costs per tonne decreased when compared to the prior-year period due to the higher volume of ore mined and milled, partially offset by higher mining costs and higher royalty costs. Production costs per ounce increased when compared to the prior-year period due to lower gold production and the timing of inventory sales, partially offset by lower production costs per tonne and the weaker Australian dollar relative to the U.S. dollar

 

Minesite and Total Cash Costs

 

Second Quarter and First Six Months of 2024 – Minesite costs per tonne decreased when compared to the prior-year periods due to a higher volume of ore mined and milled, partially offset by higher mining costs associated with the extra volume and higher royalty costs. Total cash costs per ounce increased when compared to the prior-year periods due to lower gold production, partially offset by lower minesite costs per tonne and the weaker Australian dollar relative to the U.S. dollar

 

Highlights

 

The Company continues to focus on productivity gains and cost control at the mine and the mill to maximize throughput and reduce unit costs as gold grades continue to decline with the depletion of the Swan zone. In the second quarter of 2024, Fosterville set a quarterly record in ore mined at approximately 241,000 tonnes, driven by higher than planned development in ore at Robbins Hill and Phoenix. The Company also set a monthly record in mill throughput with approximately 101,000 tonnes processed in June

 

Fosterville initiated a continuous improvement program leveraging work recently completed at Meadowbank and Meliadine and is focusing on further productivity gains at the mine and mill and on cost improvements. In the second quarter a diagnostic assessment and benchmark was completed highlighting stope cycle timing as an area of focus

 

37


 

The Company is currently advancing an upgrade of the primary ventilation system to sustain the mining rate in the Lower Phoenix zones in future years. In the second quarter of 2024, the Company continued the excavation of the ventilation raises and the project is progressing as planned at approximately 63% completion. The Company expects the project to be completed by early 2025

 

FINLAND

 

Kittila – Gold Production on Target Despite Challenges with Mill Recovery; Continuous Improvement Program Initiated

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Kittila – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     524       417       1,006       913  
Tonnes of ore milled per day     5,758       4,582       5,527       5,044  
Gold grade (g/t)     4.07       4.42       4.19       4.59  
Gold production (ounces)     55,671       50,130       110,252       113,822  
Production costs per tonne (EUR)   102     101     107     100  
Minesite costs per tonne (EUR)   101     104     106     101  
Production costs per ounce   $ 1,033     $ 864     $ 1,057     $ 849  
Total cash costs per ounce   $ 1,020     $ 899     $ 1,044     $ 847  

 

Gold Production

 

Second Quarter of 2024 – Gold production increased when compared to the prior-year period primarily due to higher throughput as the mill operated through the current period compared to a planned 10-day autoclave shutdown in the prior-year period, partially offset by lower grades and recovery

 

First Six Months of 2024 – Gold production decreased when compared to the prior-year period primarily due to lower grades and recovery, partially offset by higher throughput

 

Production Costs

 

Second Quarter of 2024 – Production costs per tonne increased slightly when compared to the prior-year period primarily due to the consumption of stockpiles in the current period compared to a build up of stockpiles in the prior-year period and higher underground mining and royalty costs, partially offset by lower mill maintenance costs in the current period. Production costs per ounce increased when compared to the prior-year period due to lower gold production and the same factors that resulted in higher production costs per tonne

 

First Six Months of 2024 – Production costs per tonne increased when compared to the prior-year period primarily due to the milling of stockpiles in the current period compared to a build up of stockpiles in the prior-year period as well as higher underground mining and royalty costs, partially offset by a higher volume of ore milled in the current period. Production costs per ounce increased when compared to the prior-year period due to lower gold production and higher production costs per tonne

 

Minesite and Total Cash Costs

 

Second Quarter of 2024 – Minesite costs per tonne decreased when compared to the prior-year period mainly due to the higher volume of ore milled in the current period, partially offset by higher underground mining and royalty costs. Total cash costs per ounce increased when compared to the prior-year period due to the lower gold production, partially offset by the same factors that resulted in lower minesite costs per tonne

 

38


 

First Six Months of 2024 – Minesite costs per tonne increased when compared to the prior-year period primarily due to higher underground mining and royalty costs, partially offset by higher volume of ore milled. Total cash costs per ounce increased when compared to the prior-year period due to lower gold production and the same factors that resulted in higher minesite costs per tonne

 

Highlights

 

Mill throughput remained on target in the second quarter of 2024, however, recovery continued to be lower than planned due to high carbon and sulphur content in the ore which affected gold production. Test trials with carbon depressant were conducted in the quarter with inconsistent results. Mineralogical modelling is ongoing and further tests will be conducted in the third quarter of 2024

 

Kittila initiated a continuous improvement program leveraging work recently completed at Meadowbank and Meliadine and is focusing on mine productivity gains and cost improvements. In the second quarter a diagnostic assessment and benchmark was completed

 

MEXICO

 

Pinos Altos – Gold Production on Target, Supported by Solid Open Pit and Mill Performance

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
Pinos Altos – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)     454       401       880       765  
Tonnes of ore milled per day     4,989       4,407       4,835       4,227  
Gold grade (g/t)     1.70       1.80       1.79       1.97  
Gold production (ounces)     23,754       22,159       48,479       46,293  
Production costs per tonne   $ 95     $ 87     $ 87     $ 88  
Minesite costs per tonne   $ 93     $ 90     $ 94     $ 91  
Production costs per ounce   $ 1,815     $ 1,566     $ 1,578     $ 1,461  
Total cash costs per ounce   $ 1,414     $ 1,282     $ 1,380     $ 1,196  

 

Gold Production

 

Second Quarter and First Six Months of 2024 – Gold production increased when compared to the prior-year periods primarily due to higher throughput, partially offset by lower gold grades as expected under the planned mining sequence

 

Production Costs

 

Second Quarter of 2024 – Production costs per tonne increased when compared to the prior-year period primarily due to a lower deferred stripping adjustment, partially offset by a higher volume of ore milled in the current period. Production costs per ounce increased when compared to the prior-year period primarily due to the same factors that resulted in higher production costs per tonne and lower gold grades

 

First Six Months of 2024 – Production costs per tonne decreased when compared to the prior-year period primarily due to a higher volume of ore milled, partially offset by a lower deferred stripping adjustment in the current period. Production costs per ounce increased when compared to the prior-year period primarily due to lower gold grades, partially offset by the same factors that resulted in lower production costs per tonne

 

Minesite and Total Cash Costs

 

Second Quarter of 2024 – Minesite costs per tonne increased when compared to the prior-year period due to the same reasons outlined above for the higher production costs per tonne. Total cash costs per ounce increased when compared to the prior-year period due to the same reasons outlined above that resulted in higher production costs per ounce

 

39


 

First Six Months of 2024 – Minesite costs per tonne increased when compared to the prior-year period primarily due to higher inventory adjustments in the period, partially offset by higher volume of ore processed. Total cash costs per ounce increased when compared to the prior-year period due to the same reasons outlined above that resulted in higher production costs per ounce and the stronger Mexican Peso relative to the U.S. dollar

 

La India – Residual Leaching to Continue Through Year-End 2024

 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
La India – Operating Statistics   2024     2023     2024     2023  
Tonnes of ore milled (thousands of tonnes)           880             1,540  
Tonnes of ore milled per day           9,670             8,508  
Gold grade (g/t)           0.74             0.72  
Gold production (ounces)     6,079       17,833       16,661       34,154  
Production costs per tonne   $     $ 27     $     $ 28  
Minesite costs per tonne   $     $ 28     $     $ 30  
Production costs per ounce   $ 2,146     $ 1,326     $ 1,742     $ 1,281  
Total cash costs per ounce   $ 2,171     $ 1,385     $ 1,715     $ 1,348  

 

Gold Production

 

Second Quarter and First Six Months of 2024 – Gold production decreased when compared to the prior-year periods due to ceasing of mining operations at La India in the fourth quarter of 2023. Gold production in the current periods came only from residual leaching

 

Costs

 

Second Quarter and First Six Months of 2024 – Production costs per ounce increased when compared to the prior-year periods driven primarily by the cessation of mining activities, partially offset by the strengthening of the Mexican Peso relative to the U.S. dollar between periods

 

Second Quarter and First Six Months of 2024 – Total cash costs per ounce increased when compared to the prior-year periods primarily due to fewer ounces of gold produced in the period

 

About Agnico Eagle

 

Agnico Eagle is a Canadian based and led senior gold mining company and the third largest gold producer in the world, producing precious metals from operations in Canada, Australia, Finland and Mexico. It has a pipeline of high-quality exploration and development projects in these countries as well as in the United States. Agnico Eagle is a partner of choice within the mining industry, recognized globally for its leading environmental, social and governance practices. The Company was founded in 1957 and has consistently created value for its shareholders, declaring a cash dividend every year since 1983.

 

About this News Release

 

Unless otherwise stated, references to “LaRonde”, “Canadian Malartic”, “Meadowbank” and "Goldex" are to the Company’s operations at the LaRonde complex, the Canadian Malartic complex, the Meadowbank complex and the Goldex complex, respectively. The LaRonde complex consists of the mill and processing operations at the LaRonde mine and the LaRonde zone 5 mine. The Canadian Malartic complex consists of the mill and processing operations at the Canadian Malartic mine and the Odyssey mine. The Meadowbank complex consists of the mill and processing operations at the Meadowbank mine and the Amaruq open pit and underground mines. The Goldex complex consists of the mill and processing operations at the Goldex mine and the Akasaba open pit mine. References to other operations are to the relevant mines, projects or properties, as applicable.

 

40


 

When used in this news release, the terms “including” and “such as” mean including and such as, without limitation.

 

The information contained on any website linked to or referred to herein (including the Company’s website) is not part of this news release.

 

Further Information

 

For further information regarding Agnico Eagle, contact Investor Relations at investor.relations@agnicoeagle.com or call (416) 947-1212.

 

Note Regarding Certain Measures of Performance

 

This news release discloses certain financial performance measures and ratios, including "total cash costs per ounce", "minesite costs per tonne", "all-in sustaining costs per ounce", "adjusted net income", "adjusted net income per share", "cash provided by operating activities before changes in non-cash working capital balances", "cash provided by operating activities before changes in non-cash working capital balances per share", "EBITDA" which means earnings before interest, taxes, depreciation and amortization, "adjusted EBITDA", "free cash flow", "free cash flow before changes in non-cash working capital balances", "operating margin", "sustaining capital expenditures", "development capital expenditures" and "net debt", as well as, for certain of these measures their related per share ratios that are not standardized measures under IFRS. These measures may not be comparable to similar measures reported by other gold producers and should be considered together with other data prepared in accordance with IFRS. See below for a reconciliation of these measures to the most directly comparable financial information reported in the consolidated financial statements prepared in accordance with IFRS.

 

Total cash costs per ounce and minesite costs per tonne

 

Total cash costs per ounce is calculated on a per ounce of gold produced basis and is reported on both a by-product basis (deducting by-product metal revenues from production costs) and co-product basis (without deducting by-product metal revenues). Total cash costs per ounce on a by-product basis is calculated by adjusting production costs as recorded in the condensed interim consolidated statements of income for by-product revenues, inventory production costs, the impact of purchase price allocation in connection with mergers and acquisitions on inventory accounting, realized gains and losses on hedges of production costs, operational care and maintenance costs due to COVID-19 and other adjustments, which include the costs associated with a 5% in-kind royalty paid in respect of certain portions of Canadian Malartic, a 2% in-kind royalty paid in respect of Detour Lake, a 1.5% in-kind royalty paid in respect of Macassa, as well as smelting, refining and marketing charges and then dividing by the number of ounces of gold produced. Given the nature of the fair value adjustment on inventory related to mergers and acquisitions and the use of the total cash costs per ounce measures to reflect the cash generating capabilities of the Company's operations, the calculations of total cash costs per ounce for Canadian Malartic has been adjusted for the purchase price allocation in the comparative period data. Investors should note that total cash costs per ounce are not reflective of all cash expenditures, as they do not include income tax payments, interest costs or dividend payments. Total cash costs per ounce on a co-product basis is calculated in the same manner as the total cash costs per ounce on a by-product basis, except that no adjustment is made for by-product metal revenues. Accordingly, the calculation of total cash costs per ounce on a co-product basis does not reflect a reduction in production costs or smelting, refining and marketing charges associated with the production and sale of by-product metals.

 

41


 

Total cash costs per ounce is intended to provide investors information about the cash-generating capabilities of the Company's mining operations. Management also uses these measures to, and believes they are useful to investors so investors can, understand and monitor the performance of the Company's mining operations. The Company believes that total cash costs per ounce is useful to help investors understand the costs associated with producing gold and the economics of gold mining. As market prices for gold are quoted on a per ounce basis, using the total cash costs per ounce on a by-product basis measure allows management and investors to assess a mine's cash-generating capabilities at various gold prices. Management is aware, and investors should note, that these per ounce measures of performance can be affected by fluctuations in exchange rates and, in the case of total cash costs per ounce on a by-product basis, by-product metal prices. Management compensates for these inherent limitations by using, and investors should also consider using, these measures in conjunction with data prepared in accordance with IFRS and minesite costs per tonne as these measures are not necessarily indicative of operating costs or cash flow measures prepared in accordance with IFRS. Management also performs sensitivity analyses in order to quantify the effects of fluctuating metal prices and exchange rates.

 

Agnico Eagle's primary business is gold production and the focus of its current operations and future development is on maximizing returns from gold production, with other metal production being incidental to the gold production process. Accordingly, all metals other than gold are considered by-products.

 

Unless otherwise indicated, total cash costs per ounce is reported on a by-product basis. Total cash costs per ounce is reported on a by-product basis because (i) the majority of the Company's revenues are from gold, (ii) the Company mines ore, which contains gold, silver, zinc, copper and other metals, (iii) it is not possible to specifically assign all costs to revenues from the gold, silver, zinc, copper and other metals the Company produces, (iv) it is a method used by management and the Board of Directors to monitor operations, and (v) many other gold producers disclose similar measures on a by-product rather than a co-product basis.

 

Minesite costs per tonne are calculated by adjusting production costs as recorded in the condensed interim consolidated statements of income for inventory production costs, operational care and maintenance costs due to COVID-19 and other adjustments, and then dividing by tonnage of ore processed. As the total cash costs per ounce can be affected by fluctuations in by-product metal prices and foreign exchange rates, management believes that minesite costs per tonne is useful to investors in providing additional information regarding the performance of mining operations, eliminating the impact of varying production levels. Management also uses this measure to determine the economic viability of mining blocks. As each mining block is evaluated based on the net realizable value of each tonne mined, in order to be economically viable the estimated revenue on a per tonne basis must be in excess of the minesite costs per tonne. Management is aware, and investors should note, that this per tonne measure of performance can be affected by fluctuations in processing levels. This inherent limitation may be partially mitigated by using this measure in conjunction with production costs and other data prepared in accordance with IFRS.

 

42


 

The following tables set out a reconciliation of total cash costs per ounce and minesite costs per tonne to production costs, exclusive of amortization, for the three and six months ended June 30, 2024 and June 30, 2023, as presented in the condensed interim consolidated statements of income in accordance with IFRS.

 

Total Production Costs by Mine

 

   

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(thousands of United States dollars)   2024     2023     2024     2023  
Quebec                        
LaRonde mine   $ 43,682     $ 63,969     $ 119,238     $ 103,676  
LaRonde zone 5 mine     20,121       21,763       39,143       43,987  
LaRonde complex     63,803       85,732       158,381       147,663  
Canadian Malartic(i)     144,333       144,190       270,909       201,481  
Goldex     33,084       28,160       66,266       55,995  
Ontario                                
Detour Lake     120,302       112,796       252,207       226,818  
Macassa     51,029       38,545       98,677       76,504  
Nunavut                                
Meliadine     85,913       78,817       179,364       160,011  
Meadowbank     123,014       117,488       237,176       247,492  
Australia                                
Fosterville     36,824       35,831       70,478       72,430  
Europe                                
Kittila     57,529       43,336       116,567       96,631  
Mexico                                
Pinos Altos     43,109       34,709       76,516       67,631  
La India     13,044       23,649       29,028       43,741  
Production costs per the condensed interim consolidated statements of income   $ 771,984     $ 743,253     $ 1,555,569     $ 1,396,397  

 

43


 

Reconciliation of Production Costs to Total Cash Costs per Ounce by Mine and Reconciliation of Production Costs to Minesite Costs per Tonne by Mine

 

(thousands of United States dollars, except as noted)

 

LaRonde mine
(per ounce)
  Three Months Ended
June 30,
     Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Gold production (ounces)             62,260               58,635               114,075               118,168  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)   ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 43,682     $ 702     $ 63,969     $ 1,091     $ 119,238     $ 1,045     $ 103,676     $ 877  
Inventory adjustments(ii)     16,244       261       (8,971 )     (153 )     1,533       14       13,534       115  
Realized gains and losses on hedges of production costs     351       5       770       13       370       3       1,848       16  
Other adjustments(v)     3,227       52       5,555       95       8,220       72       9,903       83  
Total cash costs
(co-product basis)
  $ 63,504     $ 1,020     $ 61,323     $ 1,046     $ 129,361     $ 1,134     $ 128,961     $ 1,091  
By-product metal revenues     (17,016 )     (273 )     (15,157 )     (259 )     (29,606 )     (260 )     (29,689 )     (251 )
Total cash costs
(by-product basis)
  $ 46,488     $ 747     $ 46,166     $ 787     $ 99,755     $ 874     $ 99,272     $ 840  

 

LaRonde mine
(per tonne)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Tonnes of ore milled (thousands)             381               347               794               736  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 43,682     $ 115     $ 63,969     $ 185     $ 119,238     $ 150     $ 103,676     $ 141  
Production costs (C$)    C$ 59,392     C$  156     C$  85,861     C$  247     C$  161,417     C$  203     C$  139,434     C$  189  
Inventory adjustments (C$)(iii)     23,045       60       (11,297 )     (33 )     2,731       3       18,426       25  
Other adjustments (C$)(v)     (3,264 )     (8 )     (3,302 )     (8 )     (3,600 )     (4 )     (6,443 )     (8 )
Minesite costs (C$)   C$ 79,173     C$  208     C$  71,262     C$  206     C$  160,548     C$  202      C$ 151,417     C$  206  

 

LaRonde zone 5 mine
(per ounce)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Gold production (ounces)             20,074               18,145               36,623               38,219  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 20,121     $ 1,002     $ 21,763     $ 1,199     $ 39,143     $ 1,069     $ 43,987     $ 1,151  
Inventory adjustments(ii)     (252 )     (12 )     (784 )     (43 )     68       2       (261 )     (7 )
Realized gains and losses on hedges of production costs     123       6       257       14       129       3       616       16  
Other adjustments(v)     996       50       775       43       1,366       37       1,111       29  
Total cash costs
(co-product basis)
  $ 20,988     $ 1,046     $ 22,011     $ 1,213     $ 40,706     $ 1,111     $ 45,453     $ 1,189  
By-product metal revenues     (311 )     (16 )     (271 )     (15 )     (498 )     (13 )     (546 )     (14 )
Total cash costs
(by-product basis)
  $ 20,677     $ 1,030     $ 21,740     $ 1,198     $ 40,208     $ 1,098     $ 44,907     $ 1,175  

44


 

LaRonde zone 5 mine
(per tonne)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Tonnes of ore milled (thousands)             299               313               566               632  
    (thousands)   ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 20,121     $ 67     $ 21,763     $ 70     $ 39,143     $ 69     $ 43,987     $ 70  
Production costs (C$)   C$ 27,730     C$ 93     C$ 29,277     C$ 94     C$ 53,244     C$ 94     C$ 59,265     C$ 94  
Inventory adjustments (C$)(iii)     (312 )     (1 )     (1,147 )     (4 )     120             (409 )     (1 )
Minesite costs (C$)   C$ 27,418     C$ 92     C$ 28,130     C$ 90     C$ 53,364     C$ 94     C$ 58,856     C$ 93  

 

LaRonde complex
(per ounce) 
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Gold production (ounces)             82,334               76,780               150,698               156,387  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 63,803     $ 775     $ 85,732     $ 1,117     $ 158,381     $ 1,051     $ 147,663     $ 944  
Inventory adjustments(ii)     15,992       194       (9,755 )     (127 )     1,601       11       13,273       85  
Realized gains and losses on hedges of production costs     474       6       1,027       13       499       3       2,464       16  
Other adjustments(v)     4,223       51       6,330       82       9,586       64       11,014       70  
Total cash costs (co-product basis)   $ 84,492     $ 1,026     $ 83,334     $ 1,085     $ 170,067     $ 1,129     $ 174,414     $ 1,115  
By-product metal revenues     (17,327 )     (210 )     (15,428 )     (201 )     (30,104 )     (200 )     (30,235 )     (193 )
Total cash costs (by-product basis)   $ 67,165     $ 816     $ 67,906     $ 884     $ 139,963     $ 929     $ 144,179     $ 922  

 

LaRonde complex
(per tonne) 
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Tonnes of ore milled (thousands)             680               660               1,360               1,368  
    (thousands)   ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 63,803     $ 94     $ 85,732     $ 130     $ 158,381     $ 116     $ 147,663     $ 108  
Production costs (C$)   C$ 87,122     C$ 128     C$ 115,138     C$ 174     C$ 214,661     C$ 158     C$ 198,699     C$ 145  
Inventory adjustments (C$)(iii)     22,733       34       (12,444 )     (19 )     2,851       2       18,017       13  
Other adjustments (C$)(v)     (3,264 )     (5 )     (3,302 )     (4 )     (3,600 )     (3 )     (6,443 )     (4 )
Minesite costs (C$)   C$ 106,591     C$ 157     C$ 99,392     C$ 151     C$ 213,912     C$ 157     C$ 210,273     C$ 154  

 

Canadian Malartic
(per ounce)(i) 
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Gold production (ounces)             180,871               177,755               367,777               258,440  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 144,333     $ 798     $ 144,190     $ 811     $ 270,909     $ 737     $ 201,481     $ 780  
Inventory adjustments(ii)     (5,041 )     (28 )     43             9,666       26       538       2  
Realized gains and losses on hedges of production costs     988       6                   1,040       3              
Purchase price allocation to inventory(iv)                 (22,821 )     (128 )                 (22,821 )     (88 )
In-kind royalties and other adjustments(v)     19,533       108       17,835       100       39,023       106       25,217       97  
Total cash costs
(co-product basis)
  $ 159,813     $ 884     $ 139,247     $ 783     $ 320,638     $ 872     $ 204,415     $ 791  
By-product metal revenues     (2,216 )     (13 )     (2,069 )     (11 )     (4,168 )     (12 )     (3,207 )     (12 )
Total cash costs
(by-product basis)
  $ 157,597     $ 871     $ 137,178     $ 772     $ 316,470     $ 860     $ 201,208     $ 779  

 

45


 

Canadian Malartic
(per tonne)(i) 
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Tonnes of ore milled (thousands)             5,182               4,882               10,355               7,144  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 144,333     $ 28     $ 144,190     $ 30     $ 270,909     $ 26     $ 201,481     $ 28  
Production costs (C$)   C$ 196,695     C$ 38     C$ 194,997     C$ 40     C$ 367,548     C$ 35     C$ 271,662     C$ 38  
Inventory adjustments (C$)(iii)     (6,517 )     (1 )     511             13,485       2       1,251        
Purchase price allocation to inventory (C$)(iv)                 (30,651 )     (6 )                 (30,651 )     (4 )
In-kind royalties and other adjustments (C$)(v)     26,930       5       23,599       5       52,567       5       33,424       5  
Minesite costs (C$)   C$ 217,108     C$ 42     C$ 188,456     C$ 39     C$ 433,600     C$ 42     C$ 275,686     C$ 39  

 

Goldex
(per ounce) 
 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
  2024     2023     2024     2023  
Gold production (ounces)             33,750               37,716               68,138               71,739  
                                                                 
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)       ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 33,084     $ 980     $ 28,160     $ 747     $ 66,266     $ 973     $ 55,995     $ 781  
Inventory adjustments(ii)     222       7       582       16       679       10       (455 )     (6 )
Realized gains and losses on hedges of production costs     210       6       505       13       221       3       1,212       17  
Other adjustments(v)     827       25       40       1       1,197       17       102       1  
Total cash costs
(co-product basis)
  $ 34,343     $ 1,018     $ 29,287     $ 777     $ 68,363     $ 1,003     $ 56,854     $ 793  
By-product metal revenues     (5,199 )     (154 )     (11 )     (1 )     (6,616 )     (97 )     (25 )     (1 )
Total cash costs
(by-product basis)
  $ 29,144     $ 864     $ 29,276     $ 776     $ 61,747     $ 906     $ 56,829     $ 792  

 

Goldex
(per tonne)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Tonnes of ore milled (thousands)             765               761               1,525               1,459  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 33,084     $ 43     $ 28,160     $ 37     $ 66,266     $ 43     $ 55,995     $ 38  
Production costs (C$)   C$ 45,174     C$ 59     C$ 37,859     C$ 50     C$ 89,919     C$ 59     C$ 75,486   C$ 52  
Inventory adjustments (C$)(iii)     390       1       730       1       1,039       1       (660 )     (1 )
Minesite costs (C$)   C$ 45,564     C$ 60     C$ 38,589     C$ 51     C$ 90,958     C$ 60     C$ 74,826     C$ 51  

 

Detour Lake
(per ounce) 
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Gold production (ounces)             168,247               169,352               318,998               331,209  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 120,302     $ 715     $ 112,796     $ 666     $ 252,207     $ 791     $ 226,818     $ 685  
Inventory adjustments(ii)     3,617       21       (474 )     (3 )     (4,569 )     (14 )     (168 )      
Realized gains and losses on hedges of production costs     1,089       7       2,541       15       1,147       3       6,095       18  
In-kind royalties and other adjustments(v)     8,723       52       9,410       56       16,867       53       16,985       51  
Total cash costs
(co-product basis)
  $ 133,731     $ 795     $ 124,273     $ 734     $ 265,652     $ 833     $ 249,730     $ 754  
By-product metal revenues     (666 )     (4 )     (505 )     (3 )     (1,246 )     (4 )     (1,187 )     (4 )
Total cash costs
(by-product basis)
  $ 133,065     $ 791     $ 123,768     $ 731     $ 264,406     $ 829     $ 248,543     $ 750

 

46


 

Detour Lake
(per tonne)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Tonnes of ore milled (thousands)             6,792               6,800               13,294               13,197  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 120,302     $ 18     $ 112,796     $ 17     $ 252,207     $ 19     $ 226,818     $ 17  
Production costs (C$)   C$ 164,189     C$ 24     C$ 151,645     C$ 22     C$ 342,398     C$ 26     C$ 305,553     C$ 23  
Inventory adjustments (C$)(iii)     5,253       1       12,357       2       (5,687 )           12,872       1  
In-kind royalties and other adjustments (C$)(v)     9,748       1       11,381       2       18,624       1       20,146       2  
Minesite costs (C$)   C$ 179,190     C$ 26     C$ 175,383     C$ 26     C$ 355,335     C$ 27     C$ 338,571     C$ 26  

 

Macassa
(per ounce)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Gold production (ounces)             64,062               57,044               132,321               121,159  
      (thousands)     ($ per ounce)     (thousands)   ($ per ounce)       (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 51,029     $ 797     $ 38,545     $ 676     $ 98,677     $ 746     $ 76,504     $ 631  
Inventory adjustments(ii)     (441 )     (7 )     (178 )     (3 )     (1,530 )     (12 )     (1,473 )     (11 )
Realized gains and losses on hedges of production costs     432       7       812       14       455       4       1,949       16  
In-kind royalties and other adjustments(v)     2,356       36       3,613       63       4,513       34       4,757       39  
Total cash costs
(co-product basis)
  $ 53,376     $ 833     $ 42,792     $ 750     $ 102,115     $ 772     $ 81,737     $ 675  
By-product metal revenues                 (168 )     (3 )     (220 )     (2 )     (376 )     (3 )
Total cash costs
(by-product basis)
  $ 53,376     $ 833     $ 42,624     $ 747     $ 101,895     $ 770     $ 81,361     $ 672  

 

Macassa
(per tonne)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Tonnes of ore milled (thousands)             152               112               286               199  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 51,029     $ 336     $ 38,545     $ 344     $ 98,677     $ 345     $ 76,504     $ 384  
Production costs (C$)   C$ 69,756     C$ 459     C$ 51,994     C$ 464     C$ 134,428     C$ 470     C$ 103,236     C$ 519  
Inventory adjustments (C$)(iii)     (524 )     (3 )     (359 )     (3 )     (1,940 )     (7 )     (2,076 )     (10 )
In-kind royalties and other adjustments (C$)(v)     3,138       20       4,775       42       5,953       21       6,291       30  
Minesite costs (C$)   C$ 72,370     C$ 476     C$ 56,410     C$ 503     C$ 138,441     C$ 484     C$ 107,451     C$ 539  

 

Meliadine
(per ounce)
  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
  2024     2023     2024     2023  
Gold production (ounces)             88,675               87,682               184,400               178,149  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 85,913     $ 969     $ 78,817     $ 899     $ 179,364     $ 973     $ 160,011     $ 898  
Inventory adjustments(ii)     (7,455 )     (84 )     11,228       128       (10,755 )     (58 )     14,852       83  
Realized gains and losses on hedges of production costs     827       9       (451 )     (5 )     1,107       6       (363 )     (2 )
Other adjustments(v)     93       1       (118 )     (2 )     35             (13 )      
Total cash costs
(co-product basis)
  $ 79,378     $ 895     $ 89,476     $ 1,020     $ 169,751     $ 921     $ 174,487     $ 979  
By-product metal revenues     (280 )     (3 )     (139 )     (1 )     (515 )     (3 )     (339 )     (1 )
Total cash costs
(by-product basis)
  $ 79,098     $ 892     $ 89,337     $ 1,019     $ 169,236     $ 918     $ 174,148     $ 978  

 

47


 

Meliadine   Three Months Ended
June 30,
    Six Months Ended
June 30,
 
(per tonne)   2024     2023     2024     2023  
Tonnes of ore milled (thousands)             421               461               917               937  
      (thousands)       ($ per tonne)       (thousands)       ($ per tonne)       (thousands)       ($ per tonne)       (thousands)       ($ per tonne)  
Production costs   $ 85,913     $ 204     $ 78,817     $ 171     $ 179,364     $ 196     $ 160,011     $ 171  
Production costs (C$)   C$ 116,869     C$ 278     C$ 105,834     C$ 230     C$ 242,795     C$ 265     C$ 214,715     C$ 229  
Inventory adjustments (C$)(iii)     (9,818 )     (24 )     14,556       31       (14,213 )     (16 )     19,606       21  
Minesite costs (C$)   C$ 107,051     C$ 254     C$ 120,390     C$ 261     C$ 228,582     C$ 249     C$ 234,321     C$ 250  

 

Meadowbank   Three Months Ended
June 30,
    Six Months Ended
June 30,
 
(per ounce)   2024     2023     2024     2023  
Gold production (ounces)             126,419               94,775               254,193               205,885  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 123,014     $ 973     $ 117,488     $ 1,240     $ 237,176     $ 933     $ 247,492     $ 1,202  
Inventory adjustments(ii)     (6,610 )     (52 )     (5,048 )     (54 )     (705 )     (3 )     (6,702 )     (32 )
Realized gains and losses on hedges of production costs     1,275       10       (2,118 )     (22 )     1,821       7       (3,617 )     (18 )
Other adjustments(v)     14             4             (45 )           (51 )      
Total cash costs
(co-product basis)
  $ 117,693     $ 931     $ 110,326     $ 1,164     $ 238,247     $ 937     $ 237,122     $ 1,152  
By-product metal revenues     (1,108 )     (9 )     (723 )     (8 )     (1,974 )     (7 )     (1,548 )     (8 )
Total cash costs
(by-product basis)
  $ 116,585     $ 922     $ 109,603     $ 1,156     $ 236,273     $ 930     $ 235,574     $ 1,144  

 

Meadowbank   Three Months Ended
June 30,
    Six Months Ended
June 30,
 
(per tonne)   2024     2023     2024     2023  
Tonnes of ore milled (thousands)             990               845               2,061               1,828  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 123,014     $ 124     $ 117,488     $ 139     $ 237,176     $ 115     $ 247,492     $ 135  
Production costs (C$)   C$ 167,525     C$ 169     C$ 157,407     C$ 186     C$ 321,119     C$ 156     C$ 330,385     C$ 181  
Inventory adjustments (C$)(iii)     (8,768 )     (9 )     (6,632 )     (8 )     (766 )     (1 )     (8,858 )     (5 )
Minesite costs (C$)   C$ 158,757     C$ 160     C$ 150,775     C$ 178     C$ 320,353     C$ 155     C$ 321,527     C$ 176  

 

Fosterville

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per ounce)   2024     2023     2024     2023  
Gold production (ounces)         65,963           81,813           122,532           168,371  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 36,824     $ 558     $ 35,831     $ 438     $ 70,478     $ 575     $ 72,430     $ 430  
Inventory adjustments(ii)     3,382       52       (522 )     (6 )     246       2       (2,885 )     (17 )
Realized gains and losses on hedges of production costs     68       1       489       6       86       1       677       4  
Other adjustments(v)     12             (7 )     (1 )     29             39        
Total cash costs
(co-product basis)
  $ 40,286     $ 611     $ 35,791     $ 437     $ 70,839     $ 578     $ 70,261     $ 417  
By-product metal revenues     (167 )     (3 )     (121 )     (1 )     (327 )     (3 )     (278 )     (1 )
Total cash costs
(by-product basis)
  $ 40,119     $ 608     $ 35,670     $ 436     $ 70,512     $ 575     $ 69,983     $ 416  

                                                 

Fosterville

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per tonne)   2024     2023     2024     2023  
Tonnes of ore milled (thousands)         234           176           406           324  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 36,824     $ 157     $ 35,831     $ 204     $ 70,478     $ 174     $ 72,430     $ 224  
Production costs (A$)     A$55,526       A$237       A$54,280       A$308       A$107,375       A$264       A$108,462       A$335  
Inventory adjustments (A$)(ii)     4,995       22       (756 )     (4 )     365       1       (4,357 )     (14 )
Minesite costs (A$)     A$60,521       A$259       A$53,524       A$304       A$107,740       A$265       A$104,105       A$321  

 

48


 

Kittila

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per ounce)   2024     2023     2024     2023  
Gold production (ounces)         55,671           50,130           110,252           113,822  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 57,529     $ 1,033     $ 43,336     $ 864     $ 116,567     $ 1,057     $ 96,631     $ 849  
Inventory adjustments(ii)     (649 )     (12 )     2,784       56       (1,144 )     (10 )     2,744       24  
Realized gains and losses on hedges of production costs     30       1       (925 )     (18 )     19             (1,558 )     (14 )
Other adjustments(v)     (52 )     (1 )     (50 )     (1 )     (120 )     (1 )     (1,273 )     (11 )
Total cash costs
(co-product basis)
  $ 56,858     $ 1,021     $ 45,145     $ 901     $ 115,322     $ 1,046     $ 96,544     $ 848  
By-product metal revenues     (98 )     (1 )     (93 )     (2 )     (187 )     (2 )     (162 )     (1 )
Total cash costs
(by-product basis)
  $ 56,760     $ 1,020     $ 45,052     $ 899     $ 115,135     $ 1,044     $ 96,382     $ 847  

 

Kittila

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per tonne)   2024     2023     2024     2023  
Tonnes of ore milled (thousands)         524           417           1,006           913  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 57,529     $ 110     $ 43,336     $ 104     $ 116,567     $ 116     $ 96,631     $ 106  
Production costs (€)   53,377     102     42,251     101     107,856     107     91,002     100  
Inventory adjustments (€)(iii)     (515 )     (1 )     946       3       (885 )     (1 )     832       1  
Minesite costs (€)   52,862     101     43,197     104     106,971     106     91,834     101  

 

Pinos Altos

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per ounce)   2024     2023     2024     2023  
Gold production (ounces)         23,754           22,159           48,479           46,293  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 43,109     $ 1,815     $ 34,709     $ 1,566     $ 76,516     $ 1,578     $ 67,631     $ 1,461  
Inventory adjustments(ii)     (872 )     (37 )     761       34       5,783       119       513       11  
Realized gains and losses on hedges of production costs                 (690 )     (31 )                 (1,143 )     (25 )
Other adjustments(v)     345       15       286       13       663       14       578       13  
Total cash costs
(co-product basis)
  $ 42,582     $ 1,793     $ 35,066     $ 1,582     $ 82,962     $ 1,711     $ 67,579     $ 1,460  
By-product metal revenues     (8,989 )     (379 )     (6,653 )     (300 )     (16,039 )     (331 )     (12,227 )     (264 )
Total cash costs
(by-product basis)
  $ 33,593     $ 1,414     $ 28,413     $ 1,282     $ 66,923     $ 1,380     $ 55,352     $ 1,196  

 

Pinos Altos

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per tonne)   2024     2023     2024     2023  
Tonnes of ore milled (thousands)         454           401           880           765  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 43,109     $ 95     $ 34,709     $ 87     $ 76,516     $ 87     $ 67,631     $ 88  
Inventory adjustments(iii)     (872 )     (2 )     1,905       3       5,783       7       1,657       3  
Minesite costs   $ 42,237     $ 93     $ 36,614     $ 90     $ 82,299     $ 94     $ 69,288     $ 91  

 

49


 

La India

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per ounce)   2024     2023     2024     2023  
Gold production (ounces)         6,079           17,833           16,661           34,154  
    (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)     (thousands)     ($ per ounce)  
Production costs   $ 13,044     $ 2,146     $ 23,649     $ 1,326     $ 29,028     $ 1,742     $ 43,741     $ 1,281  
Inventory adjustments(ii)     381       63       1,318       74       147       9       2,766       80  
Other adjustments(v)     131       21       134       8       264       16       263       8  
Total cash costs
(co-product basis)
  $ 13,556     $ 2,230     $ 25,101     $ 1,408     $ 29,439     $ 1,767     $ 46,770     $ 1,369  
By-product metal revenues     (356 )     (59 )     (407 )     (23 )     (858 )     (52 )     (722 )     (21 )
Total cash costs
(by-product basis)
  $ 13,200     $ 2,171     $ 24,694     $ 1,385     $ 28,581     $ 1,715     $ 46,048     $ 1,348  

 

La India

 

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
(per tonne)(vi)   2024     2023     2024     2023  
Tonnes of ore milled (thousands)                   880                     1,540  
    (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)     (thousands)     ($ per tonne)  
Production costs   $ 13,044     $     $ 23,649     $ 27     $ 29,028     $     $ 43,741     $ 28  
Inventory adjustments(iii)     (13,044 )           1,318       1       (29,028 )           2,766       2  
Minesite costs   $     $     $ 24,967     $ 28     $     $     $ 46,507     $ 30  

 

Notes:                      
(i) The information set out in this table reflects the Company's 50% interest in Canadian Malartic up to and including March 30, 2023 and 100% interest thereafter, following the closing of the Yamana Transaction.
(ii) Under the Company’s revenue recognition policy, revenue from contracts with customers is recognized upon the transfer of control over metals sold to the customer. As the total cash costs per ounce are calculated on a production basis, an inventory adjustment is made to reflect the portion of production not yet recognized as revenue.
(iii) This inventory adjustment reflects production costs associated with the portion of production still in inventory.
(iv) On March 31, 2023, the Company closed the Yamana Transaction and this adjustment reflects the fair value allocated to inventory on Canadian Malartic as part of the purchase price allocation.
(v) Other adjustments consists of costs associated with a 5% in-kind royalty paid in respect of Canadian Malartic, a 2% in-kind royalty paid in respect of Detour Lake, a 1.5% in-kind royalty paid in respect of Macassa and smelting, refining, and marketing charges to production costs.

(vi) La India’s cost calculations per tonne for the three and six months ended June 30, 2024 excludes approximately $13.0 and $29.0 million of production costs incurred during the period, respectively, following the cessation of mining activities at La India during the fourth quarter of 2023.

 

50


 

All-in sustaining costs per ounce

 

All-in sustaining costs per ounce (also referred to as "AISC per ounce") on a by-product basis is calculated as the aggregate of total cash costs on a by-product basis, sustaining capital expenditures (including capitalized exploration), general and administrative expenses (including stock options), lease payments related to sustaining assets and reclamation expenses, and then dividing by the number of ounces of gold produced. These additional costs reflect the additional expenditures that are required to be made to maintain current production levels. The AISC per ounce on a co-product basis is calculated in the same manner as the AISC per ounce on a by-product basis, except that the total cash costs on a co-product basis are used, meaning no adjustment is made for by-product metal revenues. Investors should note that AISC per ounce is not reflective of all cash expenditures as it does not include income tax payments, interest costs or dividend payments, nor does it include non-cash expenditures, such as depreciation and amortization. Unless otherwise indicated, all-in sustaining costs per ounce is reported on a by-product basis (see "Total cash costs per ounce" for a discussion of regarding the Company's use of by-product basis reporting).

 

Management believes that AISC per ounce is useful to investors as it reflects total sustaining expenditures of producing and selling an ounce of gold while maintaining current operations and, as such, provides useful information about operating performance. Management is aware, and investors should note, that these per ounce measures of performance can be affected by fluctuations in foreign exchange rates and, in the case of AISC per ounce on a by-product basis, by-product metal prices. Management compensates for these inherent limitations by using, and investors should also consider using, these measures in conjunction with data prepared in accordance with IFRS and minesite costs per tonne as this measure is not necessarily indicative of operating costs or cash flow measures prepared in accordance with IFRS.

 

The Company follows the guidance on calculation of AISC per ounce released by the World Gold Council ("WGC") in 2018. The WGC is a non-regulatory market development organization for the gold industry that has worked closely with its member companies to develop guidance in respect of relevant non-GAAP measures. Notwithstanding the Company's adoption of the WGC's guidance, AISC per ounce reported by the Company may not be comparable to data reported by other gold mining companies.

 

The following tables set out a reconciliation of production costs to all-in sustaining costs per ounce for the three and six months ended June 30, 2024 and June 30, 2023, on both a by-product basis (deducting by-product metals revenue from production costs) and co-product basis (without deducting by-product metal revenues).

 

51


 

 

Three Months Ended
June 30,

    Six Months Ended
June 30,
 
(United States dollars per ounce, except where noted)   2024     2023     2024     2023  
Production costs per the consolidated statements of income (thousands of United States dollars)   $ 771,984     $ 743,253     $ 1,555,569     $ 1,396,397  
Gold production (ounces)     895,838       873,204       1,774,490       1,686,017  
Production costs per ounce   $ 862     $ 851     $ 877     $ 828  
Adjustments:                                
Inventory adjustments(i)     3       1             14  
Purchase price allocation to inventory(ii)           (26 )           (13 )
Realized gains and losses on hedges of production costs     6       1       4       3  
Other(iii)     40       43       39       34  
Total cash costs per ounce (co-product basis)   $ 911     $ 870     $ 920     $ 866  
By-product metal revenues     (41 )     (30 )     (35 )     (30 )
Total cash costs per ounce (by-product basis)   $ 870     $ 840     $ 885     $ 836  
Adjustments:                                
Sustaining capital expenditures (including capitalized exploration)     227       237       221       226  
General and administrative expenses (including stock option expense)     54       54       55       57  
Non-cash reclamation provision and sustaining leases(iv)     18       19       18       19  
All-in sustaining costs per ounce (by-product basis)   $ 1,169     $ 1,150     $ 1,179     $ 1,138  
By-product metal revenues     41       30       35       30  
All-in sustaining costs per ounce (co-product basis)   $ 1,210     $ 1,180     $ 1,214     $ 1,168  

 

Notes:

(i)  Under the Company's revenue recognition policy, revenue from contracts with customers is recognized upon the transfer of control over metals sold to the customer. As the total cash costs per ounce are calculated on a production basis, an inventory adjustment is made to reflect the portion of production not yet recognized as revenue.

(ii)  On March 31, 2023, the Company closed the Yamana Transaction and this adjustment reflects the fair value allocated to inventory at Canadian Malartic as part of the purchase price allocation.

(iii)  Other adjustments consist of in-kind royalties, smelting, refining and marketing charges to production costs.

(iv)  Sustaining leases are lease payments related to sustaining assets.

 

Adjusted net income and adjusted net income per share

 

Adjusted net income and adjusted net income per share are calculated by adjusting the net income as recorded in the condensed interim consolidated statements of income for the effects of certain items that the Company believes are not reflective of the Company's underlying performance for the reporting period. Adjusted net income is calculated by adjusting net income for items such as foreign currency translation gains or losses, realized and unrealized gains or losses on derivative financial instruments, revaluation gains, impairment loss charges and reversals, environmental remediation, severance and transaction costs related to acquisitions, purchase price allocations to inventory, gains or losses on the disposal of assets, retroactive payments and income and mining taxes adjustments. Adjusted net income per share is calculated by dividing adjusted net income by the weighted average number of shares outstanding at the end of the period on a basic and diluted basis.

 

The Company believes that these generally accepted industry measures are useful to investors in that they allow for the evaluation of the results of continuing operations and in making comparisons between periods. Adjusted net income and adjusted net income per share are intended to provide investors with information about the Company's continuing income generating capabilities from its core mining business, excluding the above adjustments, which the Company believes are not reflective of operational performance. Management uses this measure to, and believes it is useful to investors so they can, understand and monitor for the operating performance of the Company in conjunction with other data prepared in accordance with IFRS.

 

52


 

The following tables set out a reconciliation of net income per the condensed interim consolidated statements of income to adjusted net income for the three and six months ended June 30, 2024, and June 30, 2023.

 

    Three Months Ended
June 30,
    Six Months Ended
June 30,
 
(thousands of United States dollars)   2024     2023     2024     2023  
        Restated(i)           Restated(i)  
Net income for the period - basic   $ 472,016     $ 323,670     $ 819,208     $ 2,140,561  
Dilutive impact of cash settling LTIP           (1,140 )     2,062       (2,916 )
Net income for the period - diluted   $ 472,016     $ 322,530     $ 821,270     $ 2,137,645  
Foreign currency translation loss (gain)     363       4,014       (4,184 )     4,234  
Realized and unrealized loss (gain) on derivative financial instruments     19,608       (26,433 )     65,543       (32,972 )
Transaction costs related to acquisitions           1,674             16,912  
Revaluation gain on Yamana Transaction                       (1,543,414 )
Environmental remediation     3,108       (1,420 )     4,907       (1,977 )
Net loss on disposal of property, plant and equipment     16,819       1,058       20,366       3,601  
Purchase price allocation to inventory           22,821             22,821  
Other(ii)     13,215             13,215        
Income and mining taxes adjustments(iii)     10,139       (6,121 )     (6,316 )     (19,223 )
Adjusted net income for the period - basic   $ 535,268     $ 319,263     $ 912,739     $ 590,543  
Adjusted net income for the period - diluted   $ 535,268     $ 318,123     $ 914,801     $ 587,627  

 

Notes:

(i) Certain previously reported line items have been restated to reflect the final purchase price allocation of the Yamana Transaction.

(ii) Other adjustments relate to retroactive payments that management considers not reflective of the Company's underlying performance in the current period.

(iii) Income and mining taxes adjustments reflect items such as foreign currency translation recorded to the income and mining taxes expense, the impact of income and mining taxes on adjusted items, recognition of previously unrecognized capital losses, the result of income and mining taxes audits, impact of tax law changes and adjustments to prior period tax filings.

 

EBITDA and adjusted EBITDA

 

EBITDA is calculated by adjusting the net income as recorded in the condensed interim consolidated statements of income for finance costs, amortization of property, plant and mine development and income and mining tax expense line items as reported in the condensed interim consolidated statements of income.

 

Adjusted EBITDA removes the effects of certain items that the Company believes are not reflective of the Company's underlying performance for the reporting period. Adjusted EBITDA is calculated by adjusting the EBITDA calculation for items such as foreign currency translation gains or losses, realized and unrealized gains or losses on derivative financial instruments, revaluation gains, impairment loss charges and reversals, environmental remediation, severance and transaction costs related to acquisitions, gains or losses on the disposal of assets, retroactive payments and purchase price allocations to inventory.

 

The Company believes that these generally accepted industry measures are useful in that they allow for the evaluation of the cash generating capability of the Company to fund its working capital, capital expenditure and debt repayments. EBITDA and Adjusted EBITDA are intended to provide investors with information about the Company's continuing cash generating capability from its core mining business, excluding the above adjustments, which management believes are not reflective of operational performance. Management uses these measures to, and believes it is useful to investors so they can, understand and monitor the cash generating capability of the Company in conjunction with other data prepared in accordance with IFRS.

 

53


 

The following tables set out a reconciliation of net income per the condensed interim consolidated statements of income to EBITDA and adjusted EBITDA for the three and six months ended June 30, 2024, and June 30, 2023.

 

    Three Months Ended
June 30,
    Six Months Ended
June 30,
 
(thousands of United States dollars)   2024     2023     2024     2023  
        Restated(i)           Restated(i)  
Net income for the period   $ 472,016     $ 323,670     $ 819,208     $ 2,140,561  
Finance costs     34,473       35,837       70,738       59,285  
Amortization of property, plant and mine development     378,389       386,314       735,614       690,273  
Income and mining tax expense     238,190       137,618       380,046       266,226  
EBITDA     1,123,068       883,439       2,005,606       3,156,345  
Foreign currency translation loss (gain)     363       4,014       (4,184 )     4,234  
Realized and unrealized loss (gain) on derivative financial instruments     19,608       (26,433 )     65,543       (32,972 )
Transaction costs related to acquisitions           1,674             16,912  
Revaluation gain on Yamana Transaction                       (1,543,414 )
Environmental remediation     3,108       (1,420 )     4,907       (1,977 )
Net loss on disposal of property, plant and equipment     16,819       1,058       20,366       3,601  
Purchase price allocation to inventory           22,821             22,821  
Other(ii)     13,215             13,215        
Adjusted EBITDA   $ 1,176,181     $ 885,153     $ 2,105,453     $ 1,625,550  

 

Notes:

(i) Certain previously reported line items have been restated to reflect the final purchase price allocation of the Yamana Transaction.

(ii) Other adjustments relate to retroactive payments that management considers not reflective of the Company's underlying performance in the current period.

 

Cash provided by operating activities before changes in non-cash working capital balances and cash provided by operating activities before changes in non-cash working capital balances per share

 

Cash provided by operating activities before changes in non-cash working capital balances and cash provided by operating activities before changes in non-cash working capital balances per share are calculated by adjusting the cash provided by operating activities as shown in the condensed interim consolidated statements of cash flows for the effects of changes in non-cash working capital balances such as income taxes, inventories, other current assets, accounts payable and accrued liabilities and interest payable. The per share amount is calculated by dividing cash provided by operating activities before changes in non-cash working capital balances by the weighted average number of shares outstanding at the end of the period on a basic basis. The Company believes that changes in working capital can be volatile due to numerous factors, including the timing of payments. Management uses these measures to, and believes they are useful to investors so they can, assess the underlying operating cash flow performance and future operating cash flow generating capabilities of the Company in conjunction with other data prepared in accordance with IFRS. A reconciliation of these measures to the nearest IFRS measure is provided below.

 

54


 

Free cash flow and free cash flow before changes in non-cash working capital balances

 

Free cash flow is calculated by deducting additions to property, plant and mine development from the cash provided by operating activities line item as recorded in the condensed interim consolidated statements of cash flows.

 

Free cash flow before changes in non-cash components of working capital is calculated by excluding items such as the effect of changes in non-cash components of working capital from free cash flow, which includes income taxes, inventory, other current assets, accounts payable and accrued liabilities and interest payable.

 

The Company believes that these generally accepted industry measures are useful in that they allow for the evaluation of the Company's ability to repay creditors and return cash to shareholders without relying on external sources of funding. Free cash flow and free cash flow before changes in non-cash components of working capital also provide investors with information about the Company's financial position and its ability to generate cash to fund operational and capital requirements as well as return cash to shareholders. Management uses these measures in conjunction with other data prepared in accordance with IFRS to, and believes it is useful to investors so they can, understand and monitor the cash generating ability of the Company.

 

The following tables set out a reconciliation of cash provided by operating activities per the condensed interim consolidated statements of cash flows to free cash flow and free cash flow before changes in non-cash working capital balances and to cash provided by operating activities before changes in non-cash working capital balances for the three and six months ended June 30, 2024, and June 30, 2023.

 

    Three Months Ended
June 30,
    Six Months Ended
June 30,
 
(thousands of United States dollars)   2024     2023     2024     2023  
        Restated(i)           Restated(i)  
Cash provided by operating activities   $ 961,336     $ 722,000     $ 1,744,511     $ 1,371,613  
Additions to property, plant and mine development     (404,098 )     (423,621 )     (791,685 )     (808,555 )
Free Cash Flow     557,238       298,379       952,826       563,058  
Changes in income taxes     (46,426 )     (65,428 )     (46,802 )     (89,405 )
Changes in inventory     37,028       28,815       8,856       26,747  
Changes in other current assets     84,118       102,810       57,500       83,420  
Changes in accounts payable and accrued liabilities     (47,908 )     (108,128 )     6,082       (100,859 )
Changes in interest payable     (1,900 )     12,955       (6,831 )     10,307  
Free cash flow before changes in non-cash working capital balances   $ 582,150     $ 269,403     $ 971,631     $ 493,268  
Additions to property, plant and mine development     404,098       423,621       791,685       808,555  
Cash provided by operating activities before changes in non-cash working capital balances   $ 986,248     $ 693,024     $ 1,763,316     $ 1,301,823  
                                 
Cash provided by operating activities per share - basic   $ 1.92     $ 1.46     $ 3.50     $ 2.85  
Cash provided by operating activities before changes in non-cash working capital balances per share - basic   $ 1.97     $ 1.40     $ 3.54     $ 2.70  
Free cash flow per share - basic   $ 1.12     $ 0.60     $ 1.91     $ 1.17  
                                 
Free cash flow before changes in non-cash working capital balances - basic   $ 1.17     $ 0.55     $ 1.95     $ 1.02  

 

Note:

(i) Certain previously reported line items have been restated to reflect the final purchase price allocation of the Yamana Transaction.

 

55


 

Operating margin

 

Operating margin is calculated by deducting production costs from revenue from mining operations. In order to reconcile operating margin to net income as recorded in the condensed interim consolidated financial statements, the Company adds the following items to the operating margin: income and mining taxes expense; other expenses (income); care and maintenance expenses; foreign currency translation (gain) loss; environmental remediation costs; gain (loss) on derivative financial instruments; finance costs; general and administrative expenses; amortization of property, plant and mine development; exploration and corporate development expenses; and revaluation gain and impairment losses (reversals). The Company believes that operating margin is a useful measure to investors as it reflects the operating performance of its individual mines associated with the ongoing production and sale of gold and by-product metals without allocating Company-wide overhead, including exploration and corporate development expenses, amortization of property, plant and mine development, general and administrative expenses, finance costs, gain and losses on derivative financial instruments, environmental remediation costs, foreign currency translation gains and losses, other expenses and income and mining tax expenses. Management uses this measure internally to plan and forecast future operating results. Management believes this measure is useful to investors as it provides them with additional information about the Company's underlying operating results and should be evaluated in conjunction with other data prepared in accordance with IFRS. For a reconciliation of operating margin to revenue from mining operations reported in the Company's financial statements, see "Summary of Operations Key Performance Indicators" below.

 

Sustaining capital expenditures and development capital expenditures

 

Capital expenditures are classified into sustaining capital expenditures and development capital expenditures. Sustaining capital expenditures are expenditures incurred during the production phase to sustain and maintain existing assets so they can achieve constant expected levels of production from which the Company will derive economic benefits. Sustaining capital expenditures include expenditure for assets to retain their existing productive capacity as well as to enhance performance and reliability of the operations. Development capital expenditures represent the spending at new projects and/or expenditures at existing operations that are undertaken with the intention to increase production levels or mine life above the current plans. Management uses these measures in the capital allocation process and to assess the effectiveness of its investments. Management believes these measures are useful so investors can assess the purpose and effectiveness of the capital expenditures split between sustaining and development in each reporting period. The classification between sustaining and development capital expenditures does not have a standardized definition in accordance with IFRS and other companies may classify expenditures in a different manner.

 

The following tables set out a reconciliation of sustaining capital expenditures and development capital expenditures to the additions to property, plant and mine development per the condensed interim consolidated statements of cash flows for the three and six months ended June 30, 2024 and June 30, 2023.

 

56


 

  Three Months Ended
June 30,
    Six Months Ended
June 30,
 
(thousands of United States dollars)     2024       20231       2024       20231  
Sustaining capital expenditures(ii)   $ 205,340     $ 206,914     $ 395,947     $ 381,545  
Development capital expenditures(ii)     201,962       209,133       383,373       376,236  
Total Capital Expenditures   $ 407,302     $ 416,047     $ 779,320     $ 757,781  
Working capital adjustments     (3,204 )     7,574       12,365       50,774  
Additions to property, plant and mine development per the condensed interim consolidated statements of cash flows   $ 404,098     $ 423,621     $ 791,685     $ 808,555  

 

Notes:

(i) The information set out in this table reflects the Company's 50% interest in Canadian Malartic up to and including March 30, 2023 and 100% interest thereafter.

(ii) Sustaining capital expenditures and development capital expenditures include capitalized exploration.  

 

Net debt

 

Net debt is calculated by adjusting the total of the current portion of long-term debt and non-current long-term debt as recorded on the condensed interim consolidated balance sheets for deferred financing costs and cash and cash equivalents. Management believes the measure of net debt is useful to help investors to determine the Company's overall debt position and to evaluate the future debt capacity of the Company.

 

The following tables set out a reconciliation of long-term debt per the condensed interim consolidated balance sheets to net debt as at June 30, 2024, and December 31, 2023.

 

    As at     As at  
(thousands of United States dollars)   June 30, 2024     December 31, 2023  
Current portion of long-term debt per the condensed interim consolidated balance sheets   $ 740,000     $ 100,000  
Non-current portion of long-term debt     1,101,670       1,743,086  
Long-term debt   $ 1,841,670     $ 1,843,086  
Adjustment:                
Cash and cash equivalents   $ (921,989 )   $ (338,648 )
Net Debt   $ 919,681     $ 1,504,438  

 

Forward-Looking Non-GAAP Measures

 

This news release also contains information as to estimated future total cash costs per ounce and AISC per ounce. The estimates are based upon the total cash costs per ounce and AISC per ounce that the Company expects to incur to mine gold at its mines and projects and, consistent with the reconciliation of these actual costs referred to above, do not include production costs attributable to accretion expense and other asset retirement costs, which will vary over time as each project is developed and mined. It is therefore not practicable to reconcile these forward-looking non-GAAP financial measures to the most comparable IFRS measure.

 

57


 

Forward-Looking Statements

 

The information in this news release has been prepared as at July 31, 2024. Certain statements contained in this news release constitute "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" under the provisions of Canadian provincial securities laws and are referred to herein as "forward-looking statements". All statements, other than statements of historical fact, that address circumstances, events, activities or developments that could, or may or will occur are forward-looking statements. When used in this news release, the words "achieve", "aim", "anticipate", "commit", "could", "estimate", "expect", "forecast", "future", "guide", "plan", "potential", "schedule", "target", "track", "will", and similar expressions are intended to identify forward-looking statements. Such statements include the Company's forward-looking guidance, including metal production, estimated ore grades, recovery rates, project timelines, drilling targets or results, life of mine estimates, total cash costs per ounce, AISC per ounce, minesite costs per tonne, other expenses and cash flows; the potential for additional gold production at the Company's sites; the estimated timing and conclusions of the Company's studies and evaluations; the methods by which ore will be extracted or processed; the Company's expansion plans at Detour Lake, Meliadine Phase 2, Amaruq underground, Upper Beaver and Odyssey, including the timing, funding, completion and commissioning thereof and the commencement of production therefrom; the Company's plans at Hope Bay and San Nicolás; statements concerning other expansion projects, recovery rates, mill throughput, optimization efforts and projected exploration, including costs and other estimates upon which such projections are based; timing and amounts of capital expenditures, other expenditures and other cash needs, and expectations as to the funding thereof; estimates of future mineral reserves, mineral resources, mineral production and sales; the projected development of certain ore deposits, including estimates of exploration, development and production and other capital costs and estimates of the timing of such exploration, development and production or decisions with respect to such exploration, development and production; anticipated cost inflation and its effect on the Company's costs and results; estimates of mineral reserves and mineral resources and the effect of drill results and studies on future mineral reserves and mineral resources; the Company's ability to obtain the necessary permits and authorizations in connection with its proposed or current exploration, development and mining operations, including at Meliadine, Upper Beaver and San Nicolás, and the anticipated timing thereof; future exploration; the anticipated timing of events with respect to the Company's mine sites; the Company's plans and strategies with respect to climate change and greenhouse gas emissions reductions; the sufficiency of the Company's cash resources; the Company's plans with respect to hedging and the effectiveness of its hedging strategies; future activity with respect to the Company's unsecured revolving bank credit facility, the term loan facility and other indebtedness; future dividend amounts, record dates, payment dates and discount rates under the dividend reinvestment plan; plans with respect to offering securities pursuant to the base shelf prospectus; plans with respect to activity under the NCIB; and anticipated trends with respect to the Company's operations, exploration and the funding thereof. Such statements reflect the Company's views as at the date of this news release and are subject to certain risks, uncertainties and assumptions, and undue reliance should not be placed on such statements. Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by Agnico Eagle as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The material factors and assumptions used in the preparation of the forward-looking statements contained herein, which may prove to be incorrect, include, but are not limited to, the assumptions set forth herein and in management's discussion and analysis ("MD&A") and the Company's Annual Information Form ("AIF") for the year ended December 31, 2023 filed with Canadian securities regulators and that are included in its Annual Report on Form 40-F for the year ended December 31, 2023 ("Form 40-F") filed with the U.S. Securities and Exchange Commission (the "SEC") as well as: that there are no significant disruptions affecting operations; that production, permitting, development, expansion and the ramp-up of operations at each of Agnico Eagle's properties proceeds on a basis consistent with current expectations and plans; that the relevant metal prices, foreign exchange rates and prices for key mining and construction inputs (including labour and electricity) will be consistent with Agnico Eagle's expectations; that Agnico Eagle's current estimates of mineral reserves, mineral resources, mineral grades and metal recovery are accurate; that there are no material delays in the timing for completion of ongoing growth projects; that seismic activity at the Company's operations at LaRonde, Goldex, Fosterville and other properties is as expected by the Company and that the Company's efforts to mitigate its effect on mining operations, including with respect to community relations, are successful; that the Company's current plans to address climate change and reduce greenhouse gas emissions are successful; that the Company's current plans to optimize production are successful; that there are no material variations in the current tax and regulatory environment; that governments, the Company or others do not take measures in response to pandemics or other health emergencies or otherwise that, individually or in the aggregate, materially affect the Company's ability to operate its business or its productivity; and that measures taken relating to, or other effects of, pandemics or other health emergencies do not affect the Company's ability to obtain necessary supplies and deliver them to its mine sites. Many factors, known and unknown, could cause the actual results to be materially different from those expressed or implied by such forward-looking statements. Such risks include, but are not limited to: the volatility of prices of gold and other metals; uncertainty of mineral reserves, mineral resources, mineral grades and mineral recovery estimates; uncertainty of future production, project development, capital expenditures and other costs; foreign exchange rate fluctuations; inflationary pressures; financing of additional capital requirements; cost of exploration and development programs; seismic activity at the Company's operations, including at LaRonde, Goldex and Fosterville; mining risks; community protests, including by Indigenous groups; risks associated with foreign operations; governmental and environmental regulation; the volatility of the Company's stock price; risks associated with the Company's currency, fuel and by-product metal derivative strategies; the current interest rate environment; the potential for major economies to encounter a slowdown in economic activity or a recession; the potential for increased conflict or hostilities in various regions, including Europe and the Middle East; and the extent and manner of communicable diseases or outbreaks, and measures taken by governments, the Company or others to attempt to mitigate the spread thereof may directly or indirectly affect the Company. For a more detailed discussion of such risks and other factors that may affect the Company's ability to achieve the expectations set forth in the forward-looking statements contained in this news release, see the AIF and MD&A filed on SEDAR+ at www.sedarplus.ca and included in the Form 40-F filed on EDGAR at www.sec.gov, as well as the Company's other filings with the Canadian securities regulators and the SEC. Other than as required by law, the Company does not intend, and does not assume any obligation, to update these forward-looking statements.

 

58


 

Notes Regarding Certain Climate Change and GHG Disclosure

 

This news release includes information with respect to climate change plans and strategies and GHG emissions reductions plans and strategies that has been prepared for the purpose of assisting the Company's stakeholders in understanding certain key elements of the Company's climate and other sustainability-related objectives, targets and risks and may not be suitable or appropriate for other purposes. This information has been provided from a different perspective and in more detail than is required to be included in mandatory securities filings. None of the information in this news release relating to climate change plans and strategies and GHG emissions reductions plans and strategies has been audited.

 

Due to the inherent uncertainty and limitations in measuring GHG emissions and intensity, energy consumption and composition, project type GHG reduction potential and likelihood, and climate-related risks and opportunities under the calculation methodologies used in the preparation of these and other data and metrics, all such information in this news release are estimates. There may also be differences in the manner that other parties calculate, report, test or substantiate such information compared to the Company, which means that the information reported by other parties may not be comparable to that reported by the Company. Further, as climate and other sustainability-related reporting evolves, there could be changes to the market practices, taxonomies, methodologies, criteria and standards that are used to classify, measure, test, substantiate and report on such matters, so this information may not be comparable to information prepared or reported by the Company at a different time. However, all information in this news release concerning the Company's climate and other sustainability-related objectives and impacts are based on what the Company believes to be adequate and proper substantiation in accordance with internationally recognized methodology.

 

Notes to Investors Regarding the Use of Mineral Resources

 

The mineral reserve and mineral resource estimates contained in this news release have been prepared in accordance with the Canadian securities administrators' (the "CSA") National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101").

 

In 2019, the SEC's disclosure requirements and policies for mining properties were amended to more closely align with current industry and global regulatory practices and standards, including NI 43-101. However, Canadian issuers that report in the United States using the Multijurisdictional Disclosure System ("MJDS"), such as the Company, may still use NI 43-101 rather than the SEC disclosure requirements when using the SEC's MJDS registration statement and annual report forms. Accordingly, mineral reserve and mineral resource information contained in this news release may not be comparable to similar information disclosed by U.S. companies.

 

59


 

Investors are cautioned that while the SEC recognizes "measured mineral resources", "indicated mineral resources" and "inferred mineral resources", investors should not assume that any part or all of the mineral deposits in these categories will ever be converted into a higher category of mineral resources or into mineral reserves. These terms have a great amount of uncertainty as to their economic and legal feasibility. Accordingly, investors are cautioned not to assume that any "measured mineral resources", "indicated mineral resources" or "inferred mineral resources" that the Company reports in this news release are or will be economically or legally mineable. Under Canadian regulations, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies, except in limited circumstances.

 

Further, "inferred mineral resources" have a great amount of uncertainty as to their existence and as to their economic and legal feasibility. It cannot be assumed that any part or all of an inferred mineral resource will ever be upgraded to a higher category.

 

The mineral reserve and mineral resource data set out in this news release are estimates, and no assurance can be given that the anticipated tonnages and grades will be achieved or that the indicated level of recovery will be realized. The Company does not include equivalent gold ounces for by-product metals contained in mineral reserves in its calculation of contained ounces. Mineral reserves are not reported as a subset of mineral resources.

 

Scientific and Technical Information

 

The scientific and technical information contained in this news release relating to Nunavut, Quebec and Finland operations has been approved by Dominique Girard, Eng., Executive Vice-President & Chief Operating Officer – Nunavut, Quebec & Europe; relating to Ontario, Australia and Mexico operations has been approved by Natasha Vaz, Executive Vice-President & Chief Operating Officer – Ontario, Australia & Mexico; relating to exploration has been approved by Guy Gosselin, Eng. and P.Geo., Executive Vice-President, Exploration; and relating to mineral reserves and mineral resources has been approved by Dyane Duquette, P.Geo., Vice-President, Mineral Resources Management, each of whom is a "Qualified Person" for the purposes of NI 43-101.

 

Additional Information

 

Additional information about each of the Company's material mineral projects as at December 31, 2023, including information regarding data verification, key assumptions, parameters and methods used to estimate mineral reserves and mineral resources and the risks that could materially affect the development of the mineral reserves and mineral resources required by sections 3.2 and 3.3 and paragraphs 3.4(a), (c) and (d) of NI 43-101 can be found in the Company's AIF and MD&A filed on SEDAR+ each of which forms a part of the Company's Form 40-F filed with the SEC on EDGAR and in the following technical reports filed on SEDAR+ in respect of the Company's material mineral properties: NI 43-101 Technical Report of the LaRonde complex in Québec, Canada (March 24, 2023); NI 43-101 Technical Report Canadian Malartic Mine, Québec, Canada (March 25, 2021); Technical Report on the Mineral Resources and Mineral Reserves at Meadowbank Gold complex including the Amaruq Satellite Mine Development, Nunavut, Canada as at December 31, 2017 (February 14, 2018); the Updated Technical Report on the Meliadine Gold Project, Nunavut, Canada (February 11, 2015); and the Detour Lake Operation, Ontario, Canada NI 43-101 Technical Report as at July 26, 2021 (October 15, 2021).

 

60


 

APPENDIX A – EXPLORATION DETAILS

 

MRMR update for Upper Beaver gold-copper project

 

The mineral reserves and mineral resources ("MRMR") estimate for the Upper Beaver gold-copper project in the Kirkland Lake camp in Ontario has been updated to an effective date of June 30, 2024 from the previously released MRMR estimate as at December 31, 2023, The December 2023 MRMR estimate was essentially unchanged since December 31, 2017, and was based on a historic prefeasibility study dated March 29, 2017.

 

As a result of exploration drilling campaigns conducted by the Company during the 2017 to 2022 period, additional drill results totalling 226,418 metres in 441 holes were incorporated for the first time into the June 30, 2024 MRMR update, which used a database closure date of April 3, 2024. No new drilling has been conducted at Upper Beaver since this date.

 

The updated MRMR estimate for Upper Beaver as at June 30, 2024, and the variance from the estimate as at December 31, 2023 are set out in the table below. The parameters of the updated MRMR estimate are set out in the notes of the table below.

 

Upper Beaver Mineral Reserves and Mineral Resources at June 30, 2024 and at December 31, 2023

 

    As at June 30, 20244   As at December 31, 2023   Variance  
Category    000
Tonnes
  Au
(g/t)
  Au
000 oz
  Cu
(%)
  Cu
000 t
  000
Tonnes
  Au
(g/t)
  Au
000 oz
  Cu
(%)
  Cu
000 t
  Au
000 oz
  Cu
000 t
 
Mineral Reserves                                                  
Total Proven & Probable1             7,992   5.43   1,395   0.25   20   -1,395   -20  
Mineral Resources
Indicated OP2   3,326   1.85   198   0.14   5             198   5  
Indicated UG3   27,550   3.66   3,242   0.24   66   3,636   3.45   403   0.14   5   2,838   61  
Total Indicated   30,876   3.47   3,440   0.23   71   3,636   3.45   403   0.14   5   3,036   66  
Inferred OP2                          
Inferred UG3   2,959   4.13   393   0.36   11   8,688   5.07   1,416   0.20   17   -1,023   -7  
Total Inferred   2,959   4.13   393   0.36   11   8,688   5.07   1,416   0.20   17   -1,023   -7  

 

Notes:

 

1. Mineral reserves and mineral resources as at December 31, 2023 were reported at a net smelter value cut-off of C$125/t. The assumptions used for the mineral reserve estimate as at December 2023 were US$1,200 per ounce of gold, US$2.75 per pound of copper, an exchange rate of CAD$1.25 per US$1.00 and metallurgical recoveries of 95% for gold and 90% for copper.

2. Open pit ("OP") mineral resources as at June 30, 2024 are reported at a net smelter value cut-off of C$43.49/t.

3. Underground ("UG") mineral resources as at June 30, 2024 are reported at a net smelter value cut-off of C$118.17/t. Underground mineral resources as at December 31, 2023 were reported at a net smelter value cut-off of C$125/t. Underground measured and indicated mineral resources are reported within mineable shapes and include internal and external dilution. Inferred mineral resources are reported within mineable shapes and include internal dilution. Mining and metallurgical recoveries are not applied on mineral resource.

4. The assumptions used for the mineral resource estimate as at June 30, 2024 were US$1,750 per ounce of gold, US$4.00 per pound of copper, an exchange rate of CAD$1.35 per US$1.00 used and metallurgical recoveries of 95% for gold and 83% for copper.

 

61


 

 

The main variances in the MRMR estimates between June 30, 2024, and December 31, 2023 are described below:

 

Mineral Reserves – In the updated estimate, the mineral reserves have been reclassified as mineral resources that are supported by a positive internal preliminary economic assessment, which includes both indicated mineral resources and inferred mineral resources, that was completed in June 2024. As additional geotechnical fieldwork and metallurgical test work is completed through the remainder of the year, the Company anticipates that most indicated mineral resources will be converted into probable mineral reserves at year-end 2024

 

Measured and Indicated Mineral Resources – The increase of 3.0 million ounces of gold (or 753%) and 66,000 tonnes of copper (or 1,280%) in the June 30, 2024 estimate compared to the December 31, 2023 estimate is primarily due to the incorporation of new drilling results and the reclassification of mineral reserves into indicated mineral resources

 

Inferred Mineral Resources – The decrease of 1.0 million ounces of gold (or -72%) and 7,000 tonnes of copper (or -38%) in the June 30, 2024 estimate compared to the December 31, 2023 estimate is primarily due to the successful conversion drilling program

 

Additional details on the Upper Beaver mineral reserves and mineral resources at December 31, 2023 are set out in the Company's news release dated February 15, 2024.

 

EXPLORATION DRILL COLLAR COORDINATES

 

Drill hole   UTM East*     UTM North*     Elevation
(metres above
sea level)
    Azimuth
(degrees)
    Dip
(degrees)
    Length
(metres)
 
Odyssey mine
MEX23-310ZA     718664       5334762       307       174       -61       2,050  
MEX24-311     718664       5334762       307       145       -60       2,409  
MEX24-311Z     718664       5334762       307       145       -60       2,070  
MEX24-312     718664       5334762       307       155       -74       1,753  
MEX24-312Z     718664       5334762       307       155       -74       1,777  
MEX24-314     718664       5334762       307       154       -55       1,599  
Detour Lake
DLM24-839     586805       5541735       293       177       -66       588  
DLM24-843     587883       5541783       286       178       -57       876  
DLM24-851     586844       5541744       295       176       -60       474  
DLM24-855     586962       5541810       303       179       -65       699  
DLM24-860     586848       5541874       304       178       -67       747  
DLM24-870     587168       5541594       289       177       -59       351  
DLM24-871     587284       5541663       291       176       -56       501  
DLM24-873     587162       5541698       294       176       -57       447  
DLM24-874     588888       5541621       284       178       -58       819  
DLM24-884     587283       5541869       296       174       -56       746  
DLM24-891C     588927       5541758       285       180       -65       162  
DLM24-895AW     587001       5541947       306       176       -64       567  
DLM24-897E     588036       5541696       287       179       -54       729  
DLM24-899A     587041       5541856       306       179       -64       675  

 

62


 

DLM24-903     586764       5541782       294       178       -61       633  
DLM24-908E     588764       5541748       286       180       -57       822  
DLM24-911A     587039       5541905       307       176       -69       876  
DLM24-916W     586721       5541839       295       180       -62       297  
DLM24-923     586722       5541916       299       176       -66       726  
DLM24-927     586686       5541799       292       180       -60       552  
DLM24-930A     588243       5541718       288       179       -56       948  
Hope Bay
HBM24-177B     435381       7549031       26       231       -58       1092  
HBM24-183     435244       7549203       26       237       -57       857  
HBM24-188     435572       7548364       26       235       -51       762  
HBM24-189     435502       7548335       26       229       -51       674  
HBM24-191     435391       7548479       26       245       -52       488  
HBM24-201     435024       7548255       62       88       -59       650  
HBM24-206A     434853       7548121       35       71       -52       822  
HBM24-207     434899       7548269       57       70       -68       860  
HBM24-209     434848       7548176       36       70       -65       915  

 

*Coordinate Systems: NAD 83 UTM zone 17N for Odyssey; NAD 1983 UTM zone 17N for Detour Lake; and NAD 1983 UTM zone 13N for Hope Bay

 

63


 

APPENDIX B – FINANCIAL INFORMATION

 

AGNICO EAGLE MINES LIMITED

SUMMARY OF OPERATIONS KEY PERFORMANCE INDICATORS

(thousands of United States dollars, except where noted)

 

   

Three Months Ended
June 30,

   

Six Months Ended
June 30,

 
    2024     2023     2024     2023  
          (Restated)(i)           (Restated)(i)  
Net income - key line items:                                
Revenue from mine operations:                                
Quebec                                
LaRonde mine     132,888       133,865       276,505       236,085  
LaRonde zone 5 mine     37,414       36,558       80,029       66,080  
Canadian Malartic(iii)     418,472       335,871       746,589       473,945  
Goldex     83,536       73,272       155,920       141,335  
Ontario                                
Detour Lake     359,416       317,068       702,373       623,663  
Macassa     153,476       112,879       292,869       230,738  
Nunavut                                
Meliadine     220,276       157,179       422,515       326,713  
Meadowbank     308,615       195,856       558,000       405,669  
Australia                                
Fosterville     145,026       168,074       266,061       337,375  
Europe                                
Kittila     133,160       102,868       247,223       218,887  
Mexico                                
Pinos Altos     67,790       50,389       116,190       101,837  
La India     16,552       34,318       42,170       65,531  
Revenues from mining operations   $ 2,076,621     $ 1,718,197     $ 3,906,444     $ 3,227,858  
Production costs     771,984       743,253       1,555,569       1,396,397  
Total operating margin(ii)     1,304,637       974,944       2,350,875       1,831,461  
Amortization of property, plant and mine development     378,389       386,314       735,614       690,273  
Revaluation gain(iv)                       (1,543,414 )
Exploration, corporate and other     216,042       127,342       416,007       277,815  
Income before income and mining taxes     710,206       461,288       1,199,254       2,406,787  
Income and mining taxes expense     238,190       137,618       380,046       266,226  
Net income for the period   $ 472,016     $ 323,670     $ 819,208     $ 2,140,561  
Net income per share — basic   $ 0.95     $ 0.66     $ 1.64     $ 4.45  
Net income per share — diluted   $ 0.94     $ 0.65     $ 1.64     $ 4.43  
                                 
Cash flows:                                
Cash provided by operating activities   $ 961,336     $ 722,000     $ 1,744,511     $ 1,371,613  
Cash used in investing activities   $ (424,576 )   $ (450,202 )   $ (837,624 )   $ (1,848,947 )
Cash (used in) provided by financing activities   $ (137,234 )   $ (582,351 )   $ (320,268 )   $ 254,082  
                                 
Realized prices:                                
Gold (per ounce)   $ 2,342     $ 1,975     $ 2,202     $ 1,935  
Silver (per ounce)   $ 30.09     $ 24.43     $ 27.21     $ 23.72  
Zinc (per tonne)   $ 2,792     $ 2,343     $ 2,625     $ 2,685  
Copper (per tonne)   $ 9,192     $ 7,898     $ 9,720     $ 8,590  

 

64


 

AGNICO EAGLE MINES LIMITED

SUMMARY OF OPERATIONS KEY PERFORMANCE INDICATORS

(thousands of United States dollars, except where noted)

 

   

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
    2024     2023     2024     2023  
Payable production(v):                                
Gold (ounces):                                
Quebec                                
LaRonde mine     62,260       58,635       114,075       118,168  
LaRonde zone 5 mine     20,074       18,145       36,623       38,219  
Canadian Malartic(iii)     180,871       177,755       367,777       258,440  
Goldex     33,750       37,716       68,138       71,739  
Ontario                                
Detour Lake     168,247       169,352       318,998       331,209  
Macassa     64,062       57,044       132,321       121,159  
Nunavut                                
Meliadine     88,675       87,682       184,400       178,149  
Meadowbank     126,419       94,775       254,193       205,885  
Australia                                
Fosterville     65,963       81,813       122,532       168,371  
Europe                                
Kittila     55,671       50,130       110,252       113,822  
Mexico                                
Pinos Altos     23,754       22,159       48,479       46,293  
Creston Mascota     13       165       41       409  
La India     6,079       17,833       16,661       34,154  
Total gold (ounces):     895,838       873,204       1,774,490       1,686,017  
                                 
Silver (thousands of ounces)     628       619       1,243       1,164  
Zinc (tonnes)     1,883       2,611       3,565       4,898  
Copper (tonnes)     1,072       746       1,876       1,276  

 

65


 

AGNICO EAGLE MINES LIMITED

SUMMARY OF OPERATIONS KEY PERFORMANCE INDICATORS

(thousands of United States dollars, except where noted)

 

   

Three Months Ended

June 30,

   

Six Months Ended

June 30,

 
    2024     2023     2024     2023  
Payable metal sold(vi):                                
Gold (ounces):                                
Quebec                                
LaRonde mine     51,565       61,920       116,729       110,082  
LaRonde zone 5 mine     16,265       18,923       36,516       34,384  
Canadian Malartic(iii)     176,651       168,257       336,199       240,066  
Goldex     33,783       37,114       68,225       73,031  
Ontario                                
Detour Lake     153,622       160,281       320,630       323,575  
Macassa     65,340       57,102       132,840       120,030  
Nunavut                                
Meliadine     94,438       79,153       192,978       168,739  
Meadowbank     131,003       98,980       252,113       209,005  
Australia                                
Fosterville     62,049       85,500       120,049       174,500  
Europe                                
Kittila     56,984       51,800       111,984       112,520  
Mexico                                
Pinos Altos     25,510       22,355       45,810       46,591  
La India     7,020       17,463       19,220       33,883  
Total gold (ounces):     874,230       858,848       1,753,293       1,646,406  
                                 
Silver (thousands of ounces)     637       597       1,241       1,149  
Zinc (tonnes)     1,547       2,743       3,054       4,874  
Copper (tonnes)     1,113       713       1,875       1,281  

 

66


 

AGNICO EAGLE MINES LIMITED

SUMMARY OF OPERATIONS KEY PERFORMANCE INDICATORS

(thousands of United States dollars, except where noted)

 

   

Three Months Ended
June 30,

   

Six Months Ended
June 30,

 
    2024     2023     2024     2023  
Total cash costs per ounce — co-product basis(vii):                                
Quebec                                
LaRonde mine   $ 1,020     $ 1,046     $ 1,134     $ 1,091  
LaRonde zone 5 mine     1,046       1,213       1,112       1,189  
Canadian Malartic(iii)     884       783       872       791  
Goldex     1,018       777       1,003       793  
Ontario                                
Detour Lake     795       734       833       754  
Macassa     833       750       772       675  
Nunavut                                
Meliadine     895       1,020       921       979  
Meadowbank     931       1,164       937       1,152  
Australia                                
Fosterville     611       437       578       417  
Europe                                
Kittila     1,021       901       1,046       848  
Mexico                                
Pinos Altos     1,793       1,582       1,711       1,460  
La India     2,230       1,408       1,767       1,369  
Total cash costs per ounce (co-product basis)   $ 911     $ 870     $ 920     $ 866  
                                 
Total cash costs per ounce — by-product basis(vii):                                
Quebec                                
LaRonde mine   $ 747     $ 787     $ 874     $ 840  
LaRonde zone 5 mine     1,030       1,198       1,098       1,175  
Canadian Malartic(iii)     871       772       860       779  
Goldex     864       776       906       792  
Ontario                                
Detour Lake     791       731       829       750  
Macassa     833       747       770       672  
Nunavut                                
Meliadine     892       1,019       918       978  
Meadowbank     922       1,156       930       1,144  
Australia                                
Fosterville     608       436       575       416  
Europe                                
Kittila     1,020       899       1,044       847  
Mexico                                
Pinos Altos     1,414       1,282       1,380       1,196  
La India     2,172       1,385       1,715       1,348  
Total cash costs per ounce (by-product basis)   $ 870     $ 840     $ 885     $ 836  

 

Notes:

(i)  Certain previously reported line items have been restated to reflect the final purchase price allocation of Canadian Malartic.

(ii) Operating margin is not a recognized measure under IFRS and this data may not be comparable to data reported by other gold producers. See Note Regarding Certain Measures of Performance - Operating Margin for more information on the Company's calculation and use of operating margin.

(iii) The information set out in this table reflects the Company's 50% interest in Canadian Malartic up to and including March 30, 2023 and 100% interest thereafter.

(iv) Revaluation gain on the 50% interest the Company owned in Canadian Malartic prior to the Yamana Transaction.

(v) Payable production (a non-GAAP non-financial performance measure) is the quantity of mineral produced during a period contained in products that are or will be sold by the Company, whether such products are sold during the period or held as inventories at the end of the period.

(vi) Canadian Malartic payable metal sold excludes the 5.0% in-kind net smelter return royalty held by Osisko Gold Royalties Ltd. Detour Lake payable metal sold excludes the 2.0% in-kind net smelter royalty held by Franco-Nevada Corporation. Macassa payable metal sold excludes the 1.5% in-kind net smelter royalty held by Franco-Nevada Corporation.

(vii) The total cash costs per ounce is not a recognized measure under IFRS and this data may not be comparable to data reported by other gold producers. See Note Regarding Certain Measures of Performance - Total Cash Costs per Ounce and Minesite Costs per Tonne for more information on the Company’s calculation and use of total cash cost per ounce.

 

67


 

AGNICO EAGLE MINES LIMITED

CONDENSED INTERIM CONSOLIDATED BALANCE SHEETS

(thousands of United States dollars, except share amounts, IFRS basis)

(Unaudited)

 

    As at     As at  
    June 30, 2024     December 31, 2023  
ASSETS                
Current assets:                
Cash and cash equivalents   $ 921,989     $ 338,648  
Inventories     1,355,663       1,418,941  
Income taxes recoverable     19,431       27,602  
Fair value of derivative financial instruments     5,063       50,786  
Other current assets     410,188       355,175  
Total current assets     2,712,334       2,191,152  
Non-current assets:                
Goodwill     4,157,672       4,157,672  
Property, plant and mine development     21,173,067       21,221,905  
Investments     393,867       345,257  
Deferred income and mining tax asset     31,865       53,796  
Other assets     822,401       715,167  
Total assets   $ 29,291,206     $ 28,684,949  
                 
LIABILITIES                
Current liabilities:                
Accounts payable and accrued liabilities   $ 770,802     $ 750,380  
Share based liabilities     16,730       24,316  
Interest payable     21,200       14,226  
Income taxes payable     128,940       81,222  
Current portion of long-term debt     740,000       100,000  
Reclamation provision     48,647       24,266  
Lease obligations     40,873       46,394  
Fair value of derivative financial instruments     24,032       7,222  
Total current liabilities     1,791,224       1,048,026  
Non-current liabilities:                
Long-term debt     1,101,670       1,743,086  
Reclamation provision     973,895       1,049,238  
Lease obligations     105,362       115,154  
Share based liabilities     6,851       11,153  
Deferred income and mining tax liabilities     5,045,164       4,973,271  
Other liabilities     270,625       322,106  
Total liabilities     9,294,791       9,262,034  
                 
EQUITY                
Common shares:                
Outstanding - 500,413,442 common shares issued, less 527,154 shares held in trust     18,525,686       18,334,869  
Stock options     191,200       201,755  
Contributed surplus           22,074  
Retained earnings     1,373,099       963,172  
Other reserves     (93,570 )     (98,955 )
Total equity     19,996,415       19,422,915  
Total liabilities and equity   $ 29,291,206     $ 28,684,949  

 

68


 

AGNICO EAGLE MINES LIMITED

CONDENSED INTERIM CONSOLIDATED STATEMENTS OF INCOME

(thousands of United States dollars, except per share amounts, IFRS basis)

(Unaudited)

 

   

Three Months Ended
June 30,

   

Six Months Ended
June 30,

 
    2024     2023     2024     2023  
          Restated(i)           Restated(i)  
REVENUES                                
Revenues from mining operations   $ 2,076,621     $ 1,718,197     $ 3,906,444     $ 3,227,858  
                                 
COSTS, INCOME AND EXPENSES                                
Production(ii)     771,984       743,253       1,555,569       1,396,397  
Exploration and corporate development     55,247       54,422       106,453       108,190  
Amortization of property, plant and mine development     378,389       386,314       735,614       690,273  
General and administrative     48,819       47,312       96,936       95,520  
Finance costs     34,473       35,837       70,738       59,285  
Loss (gain) on derivative financial instruments     19,608       (26,433 )     65,543       (32,972 )
Foreign currency translation loss (gain)     363       4,014       (4,184 )     4,234  
Care and maintenance     10,226       9,411       21,268       20,656  
Revaluation gain(iii)                       (1,543,414 )
Other expenses     47,306       2,779       59,253       22,902  
Income before income and mining taxes     710,206       461,288       1,199,254       2,406,787  
Income and mining taxes expense     238,190       137,618       380,046       266,226  
Net income for the period   $ 472,016     $ 323,670     $ 819,208     $ 2,140,561  
                                 
Net income per share - basic   $ 0.95     $ 0.66     $ 1.64     $ 4.45  
Net income per share - diluted   $ 0.94     $ 0.65     $ 1.64     $ 4.43  
Adjusted net income per share - basic(iv)   $ 1.07     $ 0.65     $ 1.83     $ 1.23  
Adjusted net income per share - diluted(iv)   $ 1.07     $ 0.64     $ 1.83     $ 1.22  
                                 
Weighted average number of common shares outstanding (in thousands):                                
Basic     499,437       494,138       498,528       481,553  
Diluted     500,443       495,509       499,794       482,978  

 

Notes:

(i) Certain previously reported line items have been restated to reflect the final purchase price allocation of the Yamana Transaction.

(ii) Exclusive of amortization, which is shown separately.

(iii) Revaluation gain on the 50% interest previously owned in Canadian Malartic prior to the Yamana Transaction.

(iv) Adjusted net income per share is not a recognized measure under IFRS and this data may not be comparable to data reported by other companies. See Note Regarding Certain Measures of Performance - Adjusted Net Income and Adjusted Net Income per Share for a discussion of the composition and usefulness of this measure and a reconciliation to the nearest IFRS measure.

 

69


 

AGNICO EAGLE MINES LIMITED

CONDENSED INTERIM CONSOLIDATED STATEMENTS OF CASH FLOWS

(thousands of United States dollars, IFRS basis)

(Unaudited)

 

   

Three Months Ended
June 30,

   

Six Months Ended
June 30,

 
    2024     2023     2024     2023  
          Restated(i)           Restated(i)  
OPERATING ACTIVITIES                                
Net income for the period   $ 472,016     $ 323,670     $ 819,208     $ 2,140,561  
Add (deduct) adjusting items:                                
Amortization of property, plant and mine development     378,389       386,314       735,614       690,273  
Revaluation gain(ii)                       (1,543,414 )
Deferred income and mining taxes     81,223       5,568       94,147       41,671  
Unrealized loss (gain) on currency and commodity derivatives     10,048       (50,088 )     62,532       (65,976 )
Unrealized loss (gain) on warrants     3,027       6,959       (3,850 )     2,296  
Stock-based compensation     18,858       13,380       37,715       26,527  
Foreign currency translation loss (gain)     363       4,014       (4,184 )     4,234  
Other     22,324       3,207       22,134       5,651  
Changes in non-cash working capital balances:                                
Income taxes     46,426       65,428       46,802       89,405  
Inventories     (37,028 )     (28,815 )     (8,856 )     (26,747 )
Other current assets     (84,118 )     (102,810 )     (57,500 )     (83,420 )
Accounts payable and accrued liabilities     47,908       108,128       (6,082 )     100,859  
Interest payable     1,900       (12,955 )     6,831       (10,307 )
Cash provided by operating activities     961,336       722,000       1,744,511       1,371,613  
                                 
INVESTING ACTIVITIES                                
Additions to property, plant and mine development     (404,098 )     (423,621 )     (791,685 )     (808,555 )
Yamana transaction, net of cash and cash equivalents                       (1,000,617 )
Contributions for acquisition of mineral assets     (3,175 )           (7,099 )      
Purchases of equity securities and other investments     (17,296 )     (29,427 )     (41,303 )     (44,164 )
Other investing activities     (7 )     2,846       2,463       4,389  
Cash used in investing activities     (424,576 )     (450,202 )     (837,624 )     (1,848,947 )
                                 
FINANCING ACTIVITIES                                
Proceeds from Credit Facility                 600,000       1,000,000  
Repayment of Credit Facility           (900,000 )     (600,000 )     (900,000 )
Proceeds from Term Loan Facility, net of financing costs           598,958             598,958  
Repayment of Senior Notes           (100,000 )           (100,000 )
Long-term debt financing costs                 (3,544 )      
Repayment of lease obligations     (12,666 )     (12,420 )     (25,681 )     (22,168 )
Disbursements to associates           (21,899 )           (21,899 )
Dividends paid     (164,255 )     (165,258 )     (321,515 )     (321,421 )
Repurchase of common shares     (50,000 )     (1,786 )     (76,041 )     (16,350 )
Proceeds on exercise of stock options     80,434       12,750       87,812       23,052  
Common shares issued     9,253       7,304       18,701       13,910  
Cash (used in) provided by financing activities     (137,234 )     (582,351 )     (320,268 )     254,082  
Effect of exchange rate changes on cash and cash equivalents     (2,162 )     (1,566 )     (3,278 )     (2,847 )
Net increase (decrease) in cash and cash equivalents during the period     397,364       (312,119 )     583,341       (226,099 )
Cash and cash equivalents, beginning of period     524,625       744,645       338,648       658,625  
Cash and cash equivalents, end of period   $ 921,989     $ 432,526     $ 921,989     $ 432,526  
                                 
SUPPLEMENTAL CASH FLOW INFORMATION                                
Interest paid   $ 24,651     $ 43,437     $ 49,903     $ 56,488  
Income and mining taxes paid   $ 127,600     $ 74,828     $ 258,377     $ 139,765  

 

Notes:

 

(i)  Certain previously reported line items have been restated to reflect the final purchase price allocation of the Yamana Transaction.

(ii)  Revaluation gain on the 50% interest the Company previously owned in Canadian Malartic prior to the Yamana Transaction.

 

70